13-199.00 Cameron-Reilly: Wellesley Ave & Adams Rd Sidewalks" °Fkane
Talley CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 13 -022
DEPARTMENT OF PUBLIC WORKS
3ROJECT:
Wellesley Avenue Sidewalk and Adams Road Sidewalk Project
CHANGE ORDER NO:
6
- ONTRACTOR:
Cameron - Reilly, LLC
CONTRACT DATE:
9/16/2013
PROJECT NO:
168
PO #:
43116
DESCRIPTION OF CHANGES
Change Order 6 pays Cameron Reilly force account to install a concrete retaining wall at 15911 E. Wellesley. The wall extends approximately 30' east from the
existing retaining wall.
Item No Description
154 FORCE ACCOUNT -CURB WALL CONSTRUCTION
Unit Quantity Unit Price Total
FA EST $3,000.00
Total Amount of this Change Order: $
$3,000.00
$3,000.00
SUBSTANTIAL COMPLETION
Original Date: 10/2412013 Prior to this Change Order: 10/3012013 Including this Change Order: 1118/201;
Prior Working Days: 39 Working Days Added by this CO: 1 Working Days including this CO: 4(
CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT ................................................. ...................... . ....... ........... ...........
$
- ...........................
542,200.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT
$
29,057.00
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER (through CO# 5)
....................... .$
571,257.00
NET THIS CHANGE ORDER ........... ....... _ .............. . ..................................................................... _............................................
$
3,000.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER
$
574,257.00
CONTRACTOR ACCEPTANCE: DATE: � _ 13
The contractor hereby accepts this adjustment under the t�rms of the original contract for all work performed.
RECOMMENDED BY: /.�� d L�i141�D1N4
Project Manager
APPROVED BY:
Eric Guth, Public Works Director
APPROVED BY: N/
Mike Jackson, City Manager
ATTACHMENTS: N/A
ORIGINALS TO: City of Spokane Valley Clerk's Office, Contractor
COPIES TO: PW Project File Finance dept
DATE: i Ish-3>
DATE:
DATE:
0,013-191