2013, 03-12 Permit: SW-13000200 Sewer ConnectSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW- 13000200
Permit Issued Date: 03/12/2013
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
HARRINGTON SEWER
LAUER EXCAVATION & CONST
509 - 981 -7954
Applicant: LAUER EXCAVATION & CONST
Address:
Phone:
Email:
PO BOX 11581
SPOKANE VALLEY, WA 99211
509 - 981 -7954
SITE INFORMATION:
Site Address:
Parcel Number:
8308 E ALKI AVE
45184.0555
Assessor's Description: HARRINGTONS ADD TO HUTCHINSON L5 B9
EXC S210FT
Inspection Area: : (509) -477 -3675
Zoning:
Owner:
Address:
Phone:
Email:
KINGSLEY, KYLE/ MICHAEL & LAURA
8308 E ALKI AVE
SPOKANE, WA 99212-
Water District: Hutchinson Irrigation District Fire District: Spokane Valley Fire
#16
Land Area: 12607 Square Feet
CONTRACTOR INFORMATION:
LAUEREC931DA, Exp. 03/01/2015
LAUER EXCAVATION & CONST
PO BOX 11581
SPOKANE VALLEY, WA 99211
509 - 981 -7954
DETAILS:
Class
SEWER
FEE DETAIL:
Processing - Utilities
Utilities Permit
Type
Quantity Unit Charge Value
SEWER CONNECTION
Total Fee:
$26.32
$125.00
$151.32
1 $125.00 $125.00
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1- 800 - 424 -5555 BEFORE YOU DIG - -AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477 -3604 FROM 8:30 -5:00 MONDAY - FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30- MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
Date Printed: 03/12/2013 13:39:38 Project Coordinator: Dawn Dompier
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW- 13000200 Permit Issued Date: 03/12/2013
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 03/12/2013 13:39:38
Project Coordinator: Dawn Dompier