2013, 06-26 Permit: SW-13001084 Sewer ConnectSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW- 13001084
Permit Issued Date: 06/26/2013
Expiration Date: 06/26/2014
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
HARRINGTON
OVERLAND EXCAVATION INC
509 - 939 -7984
Applicant: OVERLAND EXCAVATION INC
Address:
Phone:
Email:
5918 E TRENT AVE
SPOKANE, WA 99212
509 - 939 -7984
SITE INFORMATION:
Site Address:
Parcel Number:
Assessor's Description:
Inspection Area:
Zoning:
8711 E ALKI AVE
45184.0239
HUTHCINSON'S ADD: Lot 7 Block 18 EXCEPT the
59.82 feet thereof; EXCEPT the North 125 feet
thereof; TOGETHER WITH the East 32 feet of the
South Half of Lot 6 of Block 18
: (509)- 477 -3675
Owner:
Address:
Phone:
Email:
SHAW, JERRY LEE
8711 E ALKI
SPOKANE, WA 99212
Water District: Hutchinson Irrigation District Fire District: Spokane Valley Fire
#16
Land Area: 17037 Square Feet
CONTRACTOR INFORMATION:
OVERLEI951LE, Exp. 06/28/2014
OVERLAND EXCAVATION INC
5918 E TRENT AVE SPOKANE, WA 99212
509 - 939 -7984
DETAILS:
Class
SEWER
FEE DETAIL:
Processing - Utilities
Utilities Permit
Type
Quantity Unit Charge Value
SEWER CONNECTION
Total Fee:
$26.32
$125.00
$151.32
1 $125.00 $125.00
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1- 800 - 424 -5555 BEFORE YOU DIG - -AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477 -3604 FROM 8:30 -5:00 MONDAY - FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30- MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed: 06/26/2013 09:39:27 Project Coordinator: Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW- 13001084 Permit Issued Date: 06/26/2013
Expiration Date: 06/26/2014
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 06/26/2013 09:39:27
Project Coordinator: Kathy Cummings