14-070.00 S & L Underground: Valley Regional Decant Facility Ph 2an'
DEPARTMENT OF PUBLIC WORKS
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-009
PROJECT:- Phase 2 - Spokane Valley Regional Decant Facility
CONTRACTOR: S&L Underground, inc.
PROJECT NO: 0173
CHANGE ORDER NO: 2
CONTRACT DATE 3114/2014
PO e: 43193
DESCRIPTION OF CHANGES
This Change Order is for additional woik and materials for a 2 -inch water main tap, meter, backflow
prevention, and asphalt patch repair for permanent site water supply not included in original contract.
Bern No .Description
1 Install 2 -inch water tap, meter•, backflow prey. LS 1 .510,982.50
Unit Quantity Unit Price
Total
510,982.50
TAX 8.7% SALES TAX FOR ALL ALTERNATE BID. ITEMS
Total Amount of this •Change Order: $11,937:98
$955.48
SUBSTANTIAL COMPLETION
Original Date: 3/24/2014
Original Working Days: 110
Prior to this Change Order: 8/28/2014 Including this Change Order: 8/28/2014
Working Days Added by this CO:
0 Working Days including this CO:
110
THESE CHANGES. RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT
TOTALPRIOR CONTRACT CHANGE ORDER AMOUNT
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER
NET -THIS CHANGE ORDER
_ TOTAL, CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $
$.
5
4750,865.90
90,753.63
841,619.53
$11,937.98
853,557:51
CONTRACTOR ACCEPTANCE:
DATE:
The contactor hereby accepts this :.'ustment and the terms of the original contract for all work performed.
RECOMMENDED BY:
APPROVED BY:
APPROVED BY:
DATE: J — t -
DATE:
DATE:A(07-!/l (Y .
ATTACHMENTS:
Distribiitioh:
ORIGINALS TO: City.cif Spokane Valley Clerk's Office, Cohtra'ctor
COPIES TO: RW Project File, Finance dept
Co IL- o7o