2012, 05-17 Permit: SW-12001353 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001353
Permit Issued Date:
05/17/2012
Expiration Date:
Project Description: SEWER CONNECTION
Project Name: ROCKWELL
Permit Type: SEWER
Primary Contact: J L HAWKINS EXCAVATING
Applicant: J L HAWKINS EXCAVATING
Address: 9722 E NORA AVE
SPOKANE, WA 99206-0000
Phone: 509-924-9025
Email:
SITE INFORMATION:
Site Address: 4512 N BEST RD Owner: TRAN, HOA
Parcel Number: 45022.2310 Address: 12737 W CHARTER OAK RD
EL MIRAGE, AZ 85335
Subdivision: THROOP &
FITZPATRICK
SUBDIVISION
Assessor's Description: TRENTWDORCH THROOP&FITZ L10 B3
Inspection Area:
Phone:
Email:
Water District: Trentwood Fire District: Fire District 1
Irrigation District #3
Zoning: Land Area: 0.1653 acres / 7199 sgft
CONTRACTOR INFORMATION:
General Contractor
JLHAWE*222LE
J L HAWKINS EXCAVATING
9722 E NORA AVE
SPOKANE, WA 99206-0000
509-924-9025
DETAILS'
Class
Type
Quantity Unit Charge Value
SEWER
SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 05/17/2012 14:32:25
Printed by: IIS APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001353 05/17/2012
Expiration Date:
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.