14-122.00 Spokane Rock Products: Appleway Street Preservation c�rY of I��
Spokane
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-028
DEPARTMENT OF PUBLIC WORKS
PROJECT: Appleway Blvd Street Preservation Project CHANGE ORDER NO: 1
CONTRACTOR: Spokane Rock Products, Inc. CONTRACT DATE: 6/18/2014
PROJECT NO: 202
DESCRIPTION OF CHANGES
This Change Order deletes curb, sidewalk and pedestrian ramp work that will be demolished by the Appleway Landscaping
and Stormwater Improvement Project. The changes are shown on the attached Plan sheets 4,5 and 7,date 7-15-14.
Item No Description Unit Quantity Unit Price Total
105 REMOVE CEMENT CONCRETE CURB AND GUTTER LF -96 $9.00 -$864.00
122 CEMENT CONCRETE TRAFFIC CURB AND GUTTER LF -75 $22.00 -$1,650.00
123 CEMENT CONCRETE SIDEWALK SY -25 $26.00 -$650.00
124 CEMENT CONCRETE CURB RAMP TYPE PARALLEL A EA -2 $950.00 -$1,900.00
128 DETECTABLE WARNING SURFACE RETROFIT SF -71 $25.00 -$1,775.00
Total Amount of this Change Order: $ - -$6,839.00
Note there are changes to other bid item quantities that have less significant costs.
SUBSTANTIAL COMPLETION
Original Date: 8/29/2014 Prior to this Change Order: 8/29/2014 Including this Change Order: 8/29/2014
Original Working Days: 20 Working Days Added by this CO: 0 Working Days including this CO: 0
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 294,624.45
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 294,624.45
NET THIS CHANGE ORDER $ -$6,839.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 287,785.45
CONTRACTOR ACCEPTANCE: DATE: 7— z
The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed.
f
RECOMMENDED BY: DATE: 716 /4fProject Manager
APPROVED BY: Z-4,/vt.."/ DATE: 7/72,//1.
Enc Guth,Public Works Director
APPROVED BY: N(4 DATE:
Mike Jackson,City Manager
ATTACHMENTS: Plan Sheets 4,5&7, Dated 7-15-14
Distribution:
ORIGINALS TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor, PW Project File, Finance dept, City Manager
b0(H-122
7/1/2014