CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-028
DEPARTMENT OF PUBLIC WORKS
PROJECT Appleway Blvd Street Preservation Project CHANGE ORDER NO: 3A
CONTRACTOR Spokane Rock Products,Inc. CONTRACT DATE 8/18/2014
PROJECT NO: 202
DESCRIPTION OF CHANGES
This Change Order Supercedes and replaces Change Order 3 with a corrected Total Amount
This amended Change Order adds curb,sidewalk and pad ramp work on the northwest corner of Bradley Rd&Appleway Blvd.
The changes are shown on the attached Plan sheets 4 and 7,dated 7.30-14.
Item No peacriotion M Quantity Unit Price I2k1
105 REMOVE CEMENT CONCRETE CURB AND GUTTER LF 54 $9.00 $486.00
108 REMOVE CEMENT CONCRETE S.W.AND D.W.APPROACH SY 20 $9.00 $180.00
108 CRUSHED SURFACING TOP COURSE 2"DEPTH SY 3 $30.00 $90.00
109 CRUSHED SURFACING TOP COURSE 4"DEPTH SY 54 $15.00 $810.00
114 HMA CL.112"PG 70.28 MISC.AREAS SY 3 $225.00 $875.00
122 CEMENT CONCRETE TRAFFIC CURB AND GUTTER LF 38 $22.00 $792.00
123 CEMENT CONCRETE SIDEWALK SY 4 $26.00 $104.00
124 CEMENT CONCRETE CURB RAMP TYPE PARALLEL f EA 1 $950.00 $950.00
127 CEMENT CONCRETE PEDESTRIAN CURB LF 22 $11.50 $253.00
128 DETECTABLE WARNING SURFACE RETROFIT SF -8 $25.00 ($200.00)
201 HMA PATCH REMOVAL SY 3 $3.00 $9.00
Total Amount of this Change Order: $ - $4,149.00
SUBSTANTIAL COMPLETION
Original Date: 8/29/2014 Prior to this Change Order; 8/29/2014 Including this Change Order: 8/29/2014
Original Working Days: 20 Worldng Days Added by this CO: 0 Working Days including this CO: _ 0
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 294,824.45
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT „.....______.....$ 4839.00
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO#2 ) 290,785.45
NET THIS CHANGE ORDER „„ $ 4, 149.00
TOTAL CONTRACT AMOUNT INCLUDING IS CHANGE ORDER 294,934.45
-
CONTRACTOR ACCEPTANCE, DATE: e— 7 7
The contractor hereby accepts Ws adjustment under the terms of the original Contract for all work perfomed.
RECOMMENDED BY: ,,-----1....i•
Y: DATE: �.6 •'f . .:... ..
'r d onager
APPROVED BY: DATE: ,///// ////y
o Publto Works Direotor /
APPROVED BY: NvA DATE
Mike Jackson,City Manager