14-139.00 Spokane Rock Products: Appleway Street Preservation 1 *lame '"'J i CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-028 DEPARTMENT OF PUBLIC WORKS PROJECT Appleway Blvd Street Preservation Project CHANGE ORDER NO: 3A CONTRACTOR Spokane Rock Products,Inc. CONTRACT DATE 8/18/2014 PROJECT NO: 202 DESCRIPTION OF CHANGES This Change Order Supercedes and replaces Change Order 3 with a corrected Total Amount This amended Change Order adds curb,sidewalk and pad ramp work on the northwest corner of Bradley Rd&Appleway Blvd. The changes are shown on the attached Plan sheets 4 and 7,dated 7.30-14. Item No peacriotion M Quantity Unit Price I2k1 105 REMOVE CEMENT CONCRETE CURB AND GUTTER LF 54 $9.00 $486.00 108 REMOVE CEMENT CONCRETE S.W.AND D.W.APPROACH SY 20 $9.00 $180.00 108 CRUSHED SURFACING TOP COURSE 2"DEPTH SY 3 $30.00 $90.00 109 CRUSHED SURFACING TOP COURSE 4"DEPTH SY 54 $15.00 $810.00 114 HMA CL.112"PG 70.28 MISC.AREAS SY 3 $225.00 $875.00 122 CEMENT CONCRETE TRAFFIC CURB AND GUTTER LF 38 $22.00 $792.00 123 CEMENT CONCRETE SIDEWALK SY 4 $26.00 $104.00 124 CEMENT CONCRETE CURB RAMP TYPE PARALLEL f EA 1 $950.00 $950.00 127 CEMENT CONCRETE PEDESTRIAN CURB LF 22 $11.50 $253.00 128 DETECTABLE WARNING SURFACE RETROFIT SF -8 $25.00 ($200.00) 201 HMA PATCH REMOVAL SY 3 $3.00 $9.00 Total Amount of this Change Order: $ - $4,149.00 SUBSTANTIAL COMPLETION Original Date: 8/29/2014 Prior to this Change Order; 8/29/2014 Including this Change Order: 8/29/2014 Original Working Days: 20 Worldng Days Added by this CO: 0 Working Days including this CO: _ 0 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $ 294,824.45 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT „.....______.....$ 4839.00 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO#2 ) 290,785.45 NET THIS CHANGE ORDER „„ $ 4, 149.00 TOTAL CONTRACT AMOUNT INCLUDING IS CHANGE ORDER 294,934.45 - CONTRACTOR ACCEPTANCE, DATE: e— 7 7 The contractor hereby accepts Ws adjustment under the terms of the original Contract for all work perfomed. RECOMMENDED BY: ,,-----1....i• Y: DATE: �.6 •'f . .:... .. 'r d onager APPROVED BY: DATE: ,///// ////y o Publto Works Direotor / APPROVED BY: NvA DATE Mike Jackson,City Manager ATTACHMENTS: Revised Plan Sheet 4 and 7 Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office COPIES TO Contractor)PW Project File,Finance dept,City Manager 7/1/2014 C:fllu I��