2013, 01-09 Permit: SW-13000007 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -13000007
Permit Issued Date:
01/09/2013
Expiration Date: 01/10/2013
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
VERADALE HEIGHTS
SEWER
Primary Contact:
Applicant:
Address:
Phone:
Email:
REVIVAL PLUMBING
REVIVAL PLUMBING
P.O. BOX 10711
SPOKANE, WA 99209
509-768-2009
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
Zoning:
1425 N BOLIVAR RD
45142.3201
13TH ADDITION TO
VERADALE HEIGHTS
VERADALE HEIGHTS 13TH ADD LT 1 BLK 2 EXC
HWY
Water District:
Owner:
Address:
Phone:
Email:
BOYD, STEPHEN J
1425 N BOLIVAR RD
SPOKANE VALLEY, WA 99216
Fire District: Spokane Valley Fire
Land Area: 11398 Square Feet
CONTRACTOR INFORMATION:
General Contractor
RIVIVP*892JD
REVIVAL PLUMBING
P.O. BOX 10711
SPOKANE, WA 99209
509-768-2009
DETAILS:
Class
Type
Quantity Unit Charge
Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1
$125.00
$125.00
Total Fee:
$125.00
$26.32
$125.00
$151.32
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 01/09/2013 12:06:27
Printed by: IIS APPPOOL\SmartGovProdApp
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -13000007 01/09/2013
Expiration Date: 01/10/2013
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 01/09/2013 12:06:27 Printed by: IIS APPPOOL\SmartGovProdApp