14-159.00 Spokane Rock Products: 8th Ave Reconstruction *6o1
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-035
DEPARTMENT OF PUBLIC WORKS
PROJECT: 8th Ave Reconstruction Project CHANGE ORDER NO: 1
CONTRACTOR: Spokane Rock Products, Inc. CONTRACT DATE: 7/15/2014
PROJECT NO: 0196
DESCRIPTION OF CHANGES
The Contractor shall hand scatter and rake in dryland grass seed in swale areas using a dryland seed mix
described in the attached specification.
Item No Description Unit Quantity Unit Price Total
C01-1 Dryland Grass LS 1 $350.00 $ 350.00
Total Amount of this Change Order: $ 350.00
SUBSTANTIAL COMPLETION
Original Date: Prior to this Change Order. Including this Change Order:
Original Working Days: 0 Working Days Added by this CO: 0 Working Days including this CO: 0
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 231,865.51
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO# N/A) $ 231,865.51
NET THIS CHANGE ORDER $ 350.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 232,215.51
DATE f /
CONTRACTOR ACCEPTANCE:
The contractor hereby accepts this adjustment under the terms of the original contract for all work perfomed.
,s
RECOMMENDED BY: DATE: / 5 2-6)
Project Ma ager
APPROVED BY: � DATE 9//011
Enc u ,Pu ilc Works Direc
l
APPROVED BY: DATE:
Mike Jackson,City Manager
ATTACHMENTS:
Distribution:
ORIGINALS TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor, PW Project File, Finance dept,City Manager
7/1/2014