2014, 09-19 Permit: SW-14001379 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14001379
Permit Issued Date: 09/19/2014
Expiration Date: 09/19/2015
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
GREEN HAVEN PH 3
NORM'S EXCAVATING INC
509-928-0580
Applicant: NORM'S EXCAVATING INC
Address:
Phone:
Email: tina@normsexcavating.com
PO BOX 30873
SPOKANE, WA 99223
509-928-0580
SITE INFORMATION:
Site Address:
Parcel Number:
Assessor's Description
Inspection Area:
Zoning:
18016 E ALKI AVE
55184.1439
CORBIN ADD TO GREENACRES TR B OF SP93-
918 AUDITORS #9406170369 BK 11 PG 8 & 9
BEING A PTN OF N 1AC OF LTS 12 & 13 BLK 14
:(509)-477-3675
Owner:
Address:
Phone:
Email:
Water District: Consolidated Irrigation
District #19
ALLEN, JAMIE C & MELISSA M
18016 E ALKI AVE
GREENACRES, WA 99016
Fire District: Spokane Valley Fire
Land Area: 15380 Square Feet
CONTRACTOR INFORMATION:
NORMSEI972BM, Exp. 02/06/2015
NORM'S EXCAVATING INC
PO BOX 30873 SPOKANE, WA 99223
509-928-0580
tina@normsexcavating.com
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$26.64
$125.00
$151.64
1 $125.00 $125.00
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
Date Printed: 09/19/2014 08:25:15 Project Coordinator: Vickie Merriott