2014, 08-21 Permit: SW-14001236 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14001236
Permit Issued Date: 08/21/2014
Expiration Date: 08/21/2015
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
CRONK
LAUER EXCAVATION & CONST
509-981-7954
Applicant:
Address:
Phone:
Email:
LAUER EXCAVATION & CONST
PO BOX 11581
SPOKANE VALLEY, WA 99211
509-981-7954
SITE INFORMATION:
Site Address:
Parcel Number:
19221 E BOONE AVE
55172.0156
Owner:
Address:
Phone:
Assessor's Description: CORBIN ADDITION TO GREENACRES E 100.73FT Email:
OF PARCEL DAF; BEG AT NE COR LT 29; TH S
77DEG 18MIN W, 206.51 FT TH N 269.42FT; TH S
89DEG 20MIN 24SDS E, 201.48FT; TH S 221.70FT
TO POB, AND LOT 29
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation
District #19
Zoning:
FROMVILLER, MATTHEW
PO BOX 386
GREENACRES, WA 99016
Fire District: Spokane Valley Fire
Land Area: 1.12 Acre(s)
CONTRACTOR INFORMATION:
LAUEREC931DA, Exp. 03/01/2015
LAUER EXCAVATION & CONST
PO BOX 11581 SPOKANE VALLEY, WA 99211
509-981-7954
DETAILS:
Class
Type
SEWER
FEE DETAIL:
Processing - Utilities
Utilities Permit
SEWER CONNECTION
Total Fee:
$26.64
$125.00
$151.64
Quantity Unit Charge Value
1 $125.00 $125.00
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed: 08/21/2014 14:27:29 Project Coordinator: Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14001236 Permit Issued Date: 08/21/2014
Expiration Date: 08/21/2015
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 08/21/2014 14:27:29 Project Coordinator: Kathy Cummings