Loading...
14-174.00 Spokane Rock Products: Sprague Ave Reconstruction�o°`kane Valley. DEPARTMENT OF PUBLIC WORKS CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-029 PROJECT: Sprague Street Preservation Project CONTRACTOR: Spokane Rock Products, Inc. JECT NO: 0187 CHANGE ORDER NO: 4 CONTRACT DATE: 7/10/2014 DESCRIPTION OF CHANGES This change order provides payment for removal of delaminating grind areas and HMA prelevel at the Sprague Ave UP RR underpass. Payment will be made in accordance with WSDOT Force Account procedures. Item No Description 155 Force Account Delamination Removal and Pre -level Unit Quantity Unit Price Total Calc 1 $3,000.00 $3,000.00 Total Amount of this Change Order: $3,000.00 SUBSTANTIAL COMPLETION Original Date: Original Working Days: Prior to this Change Order: 0 Working Days Added by this CO: Including this Change Order: 0 Working Days including this CO: 0 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT ( Thru CO 3) TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER NET THIS CHANGE ORDER TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 962566.49 $ 16024.55 $ 978,591.04 $ $3,000.00 $ 981,591.04 CONTRACTOR ACCEPTANCE: The contractor hereby accepts this adjustunder the terms of the original contract for all work perfomed. RECOMMENDED BY: APPROVED BY: APPROVED BY: f oject Manager EriflGuth, Public Works Director /v/A Mike Jackson, City Manager DATE: /a -/-2a/ DATE: /01 `20/4f DATE: /0/2A4 DATE: ATTACHMENTS: Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor, PW Project File, Finance dept, City Manager 7/1/2014 ••••"%, SpaTbkane .0•OValleyg Public Works Department Capital Improvement Program 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.688-0261 • cityhall@spokanevalley.org Change Order Memorandum Date: October 1, 2014 To: Eric Guth Through: Steve Worle From: Craig Aldworth Re: Change Order 4 — Sprague St. Pres. Project, CIP 0187 Budget Account No. 311.000.187.595.30.63.00 Spokane Rock Products Contract 14-029 This Change Order pays by WSDOT Force Account for materials, equipment and labor for grinding delamination removal and HMA pre -level work on Sprague Avenue at the UP RR underpass. At the UP Railroad underpass the Contract plans call for a two inch depth grind. In areas the existing wearing course was slightly thicker. The thin layer of remaining old top course asphalt was lose. The Contractor removed the thin layer of loose asphalt down to stable HMA and then placed a thin layer of HMA pre -level to bring the bottom elevation back to a uniform 2 inch depth prior to installation of the 2 inch overlay. The change order is estimated to increase the cost of the project $3,000.00. This project is 86.5% funded by Federal Grant STPUL -3840 (010) and the 13.5% match is funded by Spokane Valley Street Preservation Fund 311. There are sufficient funds in the project budget to cover these costs. Original Contract amount = Previous Change Order Cost ( Through CO 3)= Change Order #4 Cost = Project Cost including Change Order #4 = 15% of Original Contract amount = Max Public Works Director Contract authority = Change Order Cost to date = Remaining P.W. Director Contract Authority after CO #4 Cc: Finance Department Clerk's Office $ 962,566.49 $ 16,024.55 $ 3,000.00 $ 981,591.04 $144,384.97 $75,000.00 $19,024.55 $55,975.45 StiokaneValley®~ Public Works Department Capital Improvement Program 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.921.1008 • cityhall®spokanevalley.org Change Order Memo Date: October 1, 2014 By: Craig Aldworth Re: Change Order 4 Sprague Street Preservation Project, CIP 0187 1. Describe the Change This Change Order pays by WSDOT Force Account for material, equipment and labor for removing delaminating grind areas and placing a HMA prel-evel on Sprague Ave at the UP Railroad underpass. 2. Evolution of the Change At the UP Railroad underpass the Contract plans call for a two inch depth grind. In areas the existing wearing course was slightly thicker. The thin layer of remaining old top course asphalt was lose. The Contractor removed the thin layer of loose asphalt down to stable HMA and then placed a thin layer of HMA pre -level to bring the bottom elevation back to a uniform 2 inch depth prior to installation of the 2 inch overlay. 3. Payment A $3,000.00 cost has been estimated for the additional excavation time on the attached spreadsheet. 4. Time No additional time was granted or taken away. 5. Prior Approval The Change Order was approved verbally on October 1, 2014 by Steve Worley. 6. Attachments CO 4 Force Account Estimate 10/1/14 P:\Public Works\Capital Projects\Street Projects\0187 - Sprague Ave - Vista to Herald\Construction Administration\Change Orders\C.O. #4\Force Account Spreadsheet - CO 4.xls Spokane .000Va11ey- CO 4 - Sprague St Preservation Project C. Aldworth 10/1/2014 Force Account Estimate for delam removal and HMA prelevel Sprague UP RR underpass 10/1/2014 MATERIAL COST Tons Unit Price Total 21% P&O HMA Pre -Level PRIME LABOR 8 100 800 168 Total 968.00 Trade Name Prev. Wage Rate incl. FA Labor Total Labor No. of Hours fringe FICA/FUTA/SUTP L&I' Rate 29% P&O Total Labor Cost Paver Operator 0.5 50.00 14.50 64.50 32.25 Roller Operator 0.5 50.00 14.50 64.50 32.25 Truck Driver 0.5 50.00 14.50 64.50 32.25 Asphalt Laborer 0.5 50.00 14.50 64.50 32.25 Asphalt Laborer 0.5 50.00 14.50 64.50 32.25 Asphalt Laborer 0.5 50.00 14.50 64.50 32.25 Asphalt Laborer 0.5 50.00 14.50 64.50 32.25 Prime Labor Total Cost 225.75 SUB CONTRACTOR LABOR Rate incl. FA Labor Total Labor Total Labor Trade Name No. of Hours fringe FICA/FUTA/SUTP L&1' Rate 29% P&O Rate Cost T LaRiviere Bobcat Operator 0.5 50.00 14.50 64.50 32.25 Mini Excavator Operator 0.5 50.00 14.50 64.50 32.25 Total 64.50 12% Prime Markup 7.74 Total Sub Labor Cost 72.24 Total Labor Cost 297.99 PRIME EQUIPMENT Equipment Item No. Units Unit Qty Unit Type Unit Cost 21% P&O Total Equipment Paver 0.5 200.00 42.00 121.00 Roller 0.5 100.00 21.00 60.50 Truck 0.5 50.00 10.50 30.25 Prime Eq Total Cost SUB CONTRACTOR EQUIPMENT 211.75 Equipment Item Total Total EQ Equipment Unit Qty Unit Type Unit Cost 21% P&O Rate Cost Bobcat Mini Excavator 1 1 Hr 30.00 30 6.30 36.30 36.30 Hr 20.00 20 4.20 24.20 24.20 Subcontractor EQ Total 60.50 12% Prime Markup 7.26 Subcontractor Eq Cost 67.76 Total Eq Cost 279.51 Total FA Cost 1,545.50 Contingency 1,454.50 Max Estimated Cost 3,000.00