14-189.00 Spokane Rock Products: Sprague Ave Reconstruction pOlia,ne VaeY` CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-029 DEPARTMENT OF PUBLIC WORKS PROJECT: Sprague Street Preservation Project CHANGE ORDER NO: 6 CONTRACTOR: Spokane Rock Products,Inc. CONTRACT DATE: 7/10/2014 PROJECT NO: 0187 DESCRIPTION OF CHANGES This Is an administrative change order that breaks out quantity overuns for Portable Changeable Message Signs, utility adjustments,and for work associated with stormwater work patching. Item No pescriptlon Unit Quantity Unit Price DA( 104 PORTABLE CHANGEABLE MESSAGE SIGN HR 607 $3.50 $1,774.60 134 ADJUST EXISTING CATCHBASIN OR DRYWELL EA 12 $400.00 $4,800.00 203 STORMWATER PATCH REMOVAL SY 87.6 $10.20 $893.52 210 CRUSHED SRUFACING TOP COURSE,8 IN.DEPTH SY 87.6 $17.93 $1,670.67 -• 211 HMA CL 1/2"PG 79028,0,50 FT DEPTH, PATCH SY 87.7 $86.00 $7.542.20 Total Amount of this Change Order: $15,680.89 SUBSTANTIAL COMPLETION Original Date: Prior to this Change Order: Including this Change Order: Original Working Days: 40 Working Days Added by this CO: 0 Working Days including this CO: 40 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE; ORIGINAL TOTAL CONTRACT AMOUNT — $ 962566.49 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(Thru CO 6A) $ 22806.66 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ 986,373.16 NET THIS CHANGE ORDER _ $ 16580.89 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER ,$ 1,001,954.04 CONTRACTOR ACCEPTANCE: DATE: /) -2 T'/9 The contractor hereby accepts this adjus ant under the terms of the original contract for all work perfomed. RECOMMENDED BY: ,...c. -- ' ham.. DATE: /e "23,/ e t`P a Manager APPROVED BY: 74..�.,,�2e'�Z DATE: /o/Z`v/`l " ) c Guth,Public Works Director APPROVED BY: w/ DATE: Mike Jackson,City Manager 1 ATTACHMENTS; Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Finance dept.City Manager 7/1/2014 I CO1(1- 121 01°°\41ftik Public Works Department Sjôkane Capital Improvement Program Valley - 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 .00509.921.1000 ♦ Fax: 509.688-0261 • cityhall®spokanevalley.org Change Order Memorandum Date: October 23, 2014 To: Eric Guth Through: Steve Worley From: Craig Aldworth Re: Change Order 6—Sprague St. Pres. Project, CIP 0187 Budget Account No. 311.000.187.595.30.63.00 Spokane Rock Products Contract 14-029 This is an administrative change order that pays for bid item quantity overruns for Portable Changeable Message Signs,utility adjustments, and for work associated with storm water work patching. The Change Order breaks out payment for these overruns so that the overall contract price will be increased to cover the final estimated costs. The change order is estimated to increase the cost of the project$16,580.89. This project is 86.5%funded by Federal Grant STPUL -3840 (010) and the 13.5%match is funded by Spokane Valley Street Preservation Fund 311. 13.5%of Storm water work in Schedule B, is eligible to be funded by Fund 402. There are sufficient funds in the project budget to cover these costs. Revenues: Expenditures: PE $ 51,000 Federal STP(U) Grant-86.5%$1,193,614 CE (est max total) $ 70,000 City Street Preservation $ 186,286 Construction (est max total) $1,001,954 Total Funds Available $1,379,900 Total Est. Expenditures $1,122,954 Original Contract amount= $ 962,566.49 Previous Change Order Cost(Through CO 5A)= $ 22,806.66 Change Order#6 Cost= $ 16,580.89 Project Cost including Change Order#6= $1,001,954.04 15%of Original Contract amount= $144,384.97 Max Public Works Director Contract authority= $75,000.00 Change Order Cost to date= $39,387.55 Remaining P.W. Director Contract Authority after CO #6 $35,612.45 Cc: Finance Department Clerk's Office ocikaPublic Works Department ne Capital Improvement Program Valley® 11707 E Sprague Ave Suite 106 ♦ Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.921.1008 • cityhall@spokanevalley.org Change Order Memo Date: October 23, 2014 By: Craig Aldworth Re: Change Order 6 Sprague Street Preservation Project, CIP 0187 1. Describe the Change This Change Order is an administrative change order that pays for bid item quantity overruns for Portable Changeable Message Signs, utility adjustments, and for work associated with storm water work patching. The change order breaks out payment for the overruns so the overall contract price is adequate to cover the final estimated costs. 2. Evolution of the Change Portable Changeable Message Signs (PCMS) The estimated hours for the signs did not account for possible rain or construction delays. The over-run increased the bid quantity 24.1% and the unit price was not adjusted. Utility Adjustments The utility adjustments required behind the curbs were not included in the bid item quantities. The over-run increased the bid quantity 55%. However, the increase did not justify a decrease in unit price due to economies of scale. Storm water work patching Installation of the double depth drywells in the cobble subgrade soils required larger patching areas than estimated in design in order to prevent undermining of the surrounding pavement. The over-run increased the three stormwater Sch B bid item quantities 48%. However, the increase did not justify a decrease in unit price due to economies of scale. 3. Payment The overrun cost is based on the bid item price, and is summarized below: Item # Description Over-run Unit Cost Total 104 Portable Changeable Message Sign 507 HRS $3.50/HR $1,774.50 134 Adjust Ex. CB or DW 12 EA $400/EA $4,800.00 203 Stormwater Patch Removal 87.60 SY $10.20/SY $893.52 210 CSTC 8" Depth 87.60 SY $17.93/SY $1,570.67 211 HMA CL '/2" PG 70-28 0.50' Depth, Patch 87.70 SY $86/SY $7,542.20 Total $16,580.89 The project is 86.5%funded by a Federal grant. 13.5% of the cost of Schedule A items 104 and 134 will be paid by fund 311. 13.5% of the cost of Schedule B items 203, 210 and 211 are eligible to be paid out of the storm water fund 402. 4. Time No additional time was granted or taken away by this change order. 5. Prior Approval Change Order 6 is an administrative change order. 6. Attachment None 1 1 0187-Sprague Ave Preservation Project All Activity as of Oct 23 2014 Project Prior life-= Original I Adjusted Years 2013 2014 To Date Available REVENUES Bud e� t , Budget Actual Actual Actual Actual Encumbered Funds STP(U) 1493,614.00 0.00 4,513.48 35,809.26 40,322.74 0.00 1,153,291.26 311 186,286.00 0.00 704.42 0.00 704.42 0.00 185,581.58 Total Revenue 0.00 1,379,900.00 0.00 5,217.90 35,809.26 41,027.16 0.00 1,338,872.84 Original Adjusted Prior 2013 2014 Life Available EXPENDITURES Budget Budget Years Actual Actual To Date Encumbered Funds Preliminary Engineering Salaries&Wages 52,000.00 0.00 3,948.34 18,301.81 22,250.15 0.00 29,749.85 Overtime 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Employee Benefits 18,200.00 0.00 1,269.56 5,832.60 7,102.16 0.00 11,097.84 Employee Benefits 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Engineering&Architectural 0.00 0.00 0.00 8,040.00 8,040.00 0.00 -8,040.00 Prof.Svcs-Survey 7,500.00 0.00 0.00 0.00 0.00 0.00 7,500.00 Prof.Svcs.-Geotech 5,000.00 0.00 0.00 0.00 0.00 0.00 5,000.00 Advertising 1,500.00 0.00 0.00 1,088.38 1,088.38 0.00 411.62 Printing&Binding 1,000.00 0.00 0.00 0.00 0.00 0.00 1,000.00 Miscellaneous Services 1,000.00 0.00 0.00 807.51 807.51 0.00 192.49 PE Contingency 4,000.00 0.00 0.00 0.00 0.00 0.00 4,000.00 Total Prelim.Engineering 0.00 90,200.00 0.00 5,217.90 34,070.30 39,288.20 0.00 50,911.80 Right of Way 0 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Total Right of Way 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 Construction Salaries&Wages 43,555.56 0.00 0.00 23,440.36 23,440.36 0.00 20,115.20 Overtime 0.00 0.00 0.00 3,390.12 3,390.12 0.00 -3,390.12 Employee Benefits 15,244.44 0.00 0.00 9,719.39 9,719.39 0.00 5,525.05 Employee Benefits 0.00 0.00 0.00 94.11 94.11 0.00 -94.11 Professional Services 0.00 0.00 0.00 2,580.50 2,580.50 0.00 -2,580.50 Prof.Svcs.Mat.Testing 30,000.00 0.00 0.00 9,471.58 9,471.58 8,970.42 11,558.00 Prof.Svcs.-Consulting 15,000.00 0.00 0.00 667.67 667.67 0.00 14,332.33 Advertising 1,500.00 0.00 0.00 0.00 0.00 0.00 1,500.00 Printing&Binding 1,000.00 0.00 0.00 723.42 723.42 0.00 276.58 Construction 1,099,750.00 0.00 0.00 902,553.24 902,553.24 20,335.77 176,860.99 CN Contingency 83,650.00 0.00 0.00 0.00 0.00 0.00 83,650.00 Total Construction 0.00 1,289,700.00 0.00 0.00 952,640.39 952,640.39 29,306.19 307,753.42 Total Expenditures ..:.` 0.00 1,379,900.00 0.00 : 5,217.90 986,710.69 991,928.59 P.:29,306.19 358,665.22