14-211.00 Cameron-Reilly: Sidewalk Infill Ph 2 Spokane 40,00Valleyh CHANGE ORDER NO: 2 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-012 PROJECT: Sidewalk Infill Project-Phase 2 CONTRACT DATE: 10/6/2014 PRIME CONTRACTOR: Cameron-Reilly,LLC CIP NO: 149 DESCRIPTION OF CHANGES This Change Order pertains to the project Bid Schedule. Contract quantities were increased over 125%on sod,topsoil,and river rock. This change order completes a cost adjustment to decrease prices on those items. Item No. Description Unit Quantity Unit Price Total 145 Top Soil,Type B SY -42 $ 15.00 $ (630.00) 146 Sod Installation SY -42 $ 25.00 $ (1,050.00) 148 River Rock SY -2 $ 100.00 $ (200.00) 155 Top Soil,Type B SY 124 $ 13.20 $ 1,636.80 156 Sod Installation SY 124 $ 19.80 $ 2,455.20 157 River Rock SY 18 $ 27.50 $ 495.00 8.7%Sales Tax $ N/A Total Amount of this Change Order(incl.Tax): $ 2,707.00 PHYSICAL COMPLETION Original Contract Working Days: 20 Revision By This Change Order: 0 Revisions by Prior Change Orders: 1 Total Revised Contract Working Days: 21 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 208 937.20 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#t) $ 875.00 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER .....__...._.. _ $ 209,812.20 NET THIS CHANGE ORDER ._._....._...:............._.........._._ $ 2,707.00 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 212,519.20 CONTRACTOR ACCEPTANCE: DATE: /17 z-/4--- The contractor hereby accepts this ai stment under the terms of Section 1-04.4 of the original contract. RECOMMENDED BY: 1 &4t.gi,t DATE: Project Manager APPROVED BY: DATE: ////Z/V Public Works Director APPROVED BY: N/A DATE: City Manager ATTACHMENTS: N/A Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department COS''1 r"-or::)c,5'2 i4