14-217.00 Stone Creek Land Design & Development Spokane
4000 Valley
CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-047
DEPARTMENT OF PUBLIC WORKS
PROJECT: APPLEWAY TRAIL PHASE 2A (PAVING) CHANGE ORDER NO: 2
CONTRACTOR: STONE CREEK LAND DESIGN AND DEVELOPMENT,LLC CONTRACT DATE: Sept.29,2014
PROJECT NO: 0176
DESCRIPTION OF CHANGES
This Change Order adds an additional Double Check Valve Assembly to isolate the irrigation system from the potable water
system. See attached description and drawing.
Item No Description Unit Quantity Unit Price Total
CO-2 DCVA-Irrigation System LS 1 1,549.50 $ 1,549.50
Total Amount of this Change Order: $ 1,549.50
SUBSTANTIAL COMPLETION
Original Date: Prior to this Change Order: Including this Change Order:
Original Working Days: 90 Working Days Added by this CO: 0 Working Days including this CO: 0
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL TOTAL CONTRACT AMOUNT $ 1,069,082.75
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT - $ 5,973.72
TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO#1 ) $ 1,075,056.47
NET THIS CHANGE ORDER $ 1,549.50
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,076,605.97
CONTRACTOR ACCEPTANCE: fC(•—•---` •..._ DATE: \ k--- I 1f
The contractor hereby accepts this a•�,t sent under the terms of
the original contract for all work perfomed. / / /
�� / jpe/ DATE: l/�l 7�!
RECOMMENDED BY: /%���
Project Manager
s
APPROVED BY: ,':,,e1,10;/- 7�:� DATE: ///'�,/il
nc Guth,Public Works Director
APPROVED BY: NWA DATE:
Mike Jackson,City Manager
ATTACHMENTS:
Distribution: t
ORIGINALS TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Finance dept,City Manager
0.011-1-217