14-218.00 Stone Creek Land Design & Development Spokane 40000 ValleY CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-047 DEPARTMENT OF PUBLIC WORKS PROJECT: APPLEWAY TRAIL PHASE 2A (PAVING) CHANGE ORDER NO: 3 CONTRACTOR: STONE CREEK LAND DESIGN AND DEVELOPMENT,LLC CONTRACT DATE: Sept.29,2014 PROJECT NO: 0176 DESCRIPTION OF CHANGES This Change Order adds two additional Rama Light fixtures. These are added to the existing light poles in the Valley Glass parking lot. Item No Description Unit Quantity Unit Price Total CO-3 Additonal Rama Light Fixtures L.S. 1 6,608.00 $ 6,608.00 Total Amount of this Change Order: $ 6,608.00 SUBSTANTIAL COMPLETION Original Date: Prior to this Change Order: Including this Change Order: Original Working Days: 90 Working Days Added by this CO: 0 Working Days including this CO: 0 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $ 1,069,082.75 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 7,523.22 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER(through CO#1 ) $ 1,076,605.97 NET THIS CHANGE ORDER $ 6,608.00 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,083,213.97 CONTRACTOR ACCEPTANCE: J DATE: The contractor hereby accepts this a•jus1 ent un er h-to s of the original contract for all work perfomed. RECOMMENDED BY: - ‘a i DATE: i` // 6//4 Project Manager APPROVED BY: "‘./11..4.2e DATE: I77/ th,Public Works Director APPROVED BY: AJ/4 DATE: Mike Jackson,City Manager ATTACHMENTS: Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Finance dept,City Manager