2012, 12-03 Permit: SW-12002587 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002587
Permit Issued Date:
12/03/2012
Expiration Date:
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
ELECTRIC R/R
SEWER
Primary Contact: LARRY MILLER EXCAVATING
Applicant: LARRY MILLER EXCAVATING
Address:
Phone:
Email:
7117 E RUTTER AVE
SPOKANE, WA 99212
509-218-3335
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
Zoning:
7811 E BUCKEYE AVE
45072.0908
ELECTRIC RAILWAY
SUBURBAN HOME
ADDITION
ELEC RY SUB HOME PT OF B9 BEG 20FT N &
93FT W OF SECOR TH N8OFT PAR TO EL TH
NWLY TO NWCOR OF E149FT OF S1/2 TH S PAR
TO EL TO PT 20FT N OF SL TH E TO POB
Owner:
Address:
Phone:
Email:
BOGERT, PETER R & PAULINE K
7811 E BUCKEYE AVE
SPOKANE, WA 99212
Water District: Orchard Fire District: Spokane Valley Fire
Avenue Irrigation District
#6
Land Area: 6750 Square Feet
CONTRACTOR INFORMATION:
General Contractor
LARRYME918DR
LARRY MILLER EXCAVATING
7117 E RUTTER AVE
SPOKANE, WA 99212
509-218-3335
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1
$125.00 $125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Date Printed: 12/03/2012 11:39:29
Printed by: IIS APPPOOL\SmartGovProdApp
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002587
Inside Public Transit Benefit Area
Permit Issued Date:
12/03/2012
Expiration Date:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 12/03/2012 11:39:29 Printed by: IIS APPPOOL\SmartGovProdApp