2013, 03-04 Permit: SW-13000131 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -13000131
Permit Issued Date: 03/04/2013
Project Description:
Project Name:
Primary Contact:
Phone:
SEWER CONNECTION
ELECTRIC RR
MUELLER EXCAVATING
509-326-1016
Applicant: MUELLER EXCAVATING
Address:
Phone:
Email:
3743 W OLYMPIC AVE
SPOKANE, WA 99205
509-326-1016
SITE INFORMATION:
Site Address:
Parcel Number:
2714 N ELLA RD
45072.4809
Assessor's Description: ORCHARD AVE ADD REPLAT BLK 151 TO 154-
178-179&225 PTN 0 F BLKS 258 & 265 DAF; BEG
AT A PT ON W LN OF SD BLK 258 WHICH I S 73' S
OF THE NW COR THEREOF; TH E92' TH S32' TH
E58.75' TH S6 3' TH W150.75' T
Inspection Area: : (509)-477-3675
Zoning:
Owner:
Address:
Phone:
Email:
Water District: Orchard Avenue Irrigation
District #6
THOMAS, C R
8412 N STEVENS ST
SPOKANE, WA 99208
Fire District: Spokane Valley Fire
Land Area: 12476.5 Square Feet
CONTRACTOR INFORMATION:
MUELLE*181KK, Exp. 03/01/2014
MUELLER EXCAVATING
3743 W OLYMPIC AVE
SPOKANE, WA 99205
509-326-1016
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$26.32
$125.00
$151.32
1 $125.00 $125.00
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 03/04/2013 13:37:25 Project Coordinator: Dawn Dompier
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -13000131 Permit Issued Date: 03/04/2013
INSTALLER !S RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19,122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 03/04/2013 13:37:25 Project Coordinator: Dawn Dompier