14-233.00 Inland Asphalt: 2014 Stormwater Utility Small Works Projects Spokane FValley CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-051 DEPARTMENT OF PUBLIC WORKS PROJECT: SW Utility 2014 Small Works, Package 2 CHANGE ORDER NO: 1 CONTRACTOR: Inland Asphalt Company CONTRACT DATE: 9/22/2014 PROJECT NO: n/a DESCRIPTION OF CHANGES This change order is for: 1.work completed by the contractor to determine if the phone, power,and gas would be a problem for the depth of the improvements proposed for the Bowdish location(Item 9 below) 2. document suspension of work due to winter shut down-new substantial completion date 3.acknowledgement that a Variable Messaging Sign (VMS)was placed by the contractor prior to winter shut down for several weeks on Wellesley,just east of Sullivan, per project plan,and the contractor has met this contractual requirement. Additional need for VMS in the spring prior to recommencing the work will be Item No Description Unit Quantity Unit Price Total 9 Pothole Utility Locations for Depth(+ 12% markup) 1 LS $730.46 $730.46 Total Amount of this Change Order: $730.46 SUBSTANTIAL COMPLETION Original Date: 11/12/2014 Prior to this Change Order: 11/12/2014 Including this Change Order: 4/14/2015 Original Working Days: 10 Working Days Added by this CO: 0 Vorking Days including this CO: 10 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $152,077.00 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $0.00 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $152,077.00 NET THIS CHANGE ORDER $730.46 TOTAL CONTRACT AMOUNT INCLUDING THIS rCHANGE ORDER $152,807.46 CONTRACTOR ACCEPTANCE: 1 / DATE: The contractor hereby accepts this adju tment under t - oft'e original contract for all work perfomed. � r Q RECOMMENDED BY: i — DATE: 1Z?c.,�.�VGC Zo(4 Project Manager APPROVED BY: `%llf - DATE: 2/I 7/7 c Guth,Public Works Director APPROVED BY: Af/ DATE: Mike Jackson,City Manager ATTACHMENTS: Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor, PW Project File, Finance dept,City Manager //1/2014 (ou-223 ,ter S" 'OF Works Department okPublic Stormwater Utility _ Valley 11707 E Sprague Ave Suite 106 • Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.688-0261 • cityhall@spokanevalley.org Change Order Memorandum Date: December 4,2014 To: Eric Guth From: Art Jenkins, PE, CSM Re: Change Order#1 for SW Utility 2014 all Works, Package 2, Contract#14-051 Budget Account No. 402.402.000.595.40.63.00 Inland Asphalt Company, Inc., Contract 14- 051 1. Additional work to locate phone,power, and gas depths along Bowdish and within the project limits to determine if the construction depth would encounter these utilities. No additional time will be granted as a result of this change order. This work came in below our independent estimate of$1,000. There are sufficient funds in the project budget to cover this change order. Original Contract amount= $ 152,077.00 Previous Change Order Cost= $ 0.00 Change Order#1 Cost= $ 730.46 Project Cost including Change Order#1 = $ 152,807.46 15% of Original Contract amount= $ 22,811.55 Max Public Works Director Contract authority= $ 22,811.55 ($75,000 or 15%of original contract amount, whichever is less) Change Order Cost to date= $ 730.46 Remaining P.W. Director Contract Authority after CO#1 $ 22,081.09 cc: Finance Department Clerk's office