14-044.04 S & L Underground: Valley Regional Decant Facility Ph 2 crrec +t�ir4 CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 14-009 DEPARTMENT OF PUBLIC WORKS PROJECT: Phase 2-Spokane Valley Regional Decant Facility CHANGE ORDER NO: 4 CONTRACTOR: S&L Underground,Inc. CONTRACT DATE: 3/14/2014 PROJECT NO: 0173 PO#: 43193 DESCRIPTION OF CHANGES This final change order balances extensions/deletions of actual quantities used on the project. It also resolves several issues to meet Electrical LNI,Fire Department,WSDOT,and OSHA requirements for the snow melt,gate,and access controls systems. Item No Description Unit Quantity Unit Price Total 22a Snow Melt Sys Pull box aQ col 86,Conduit LS 1 $4,200.00 $4,200.00 22b Snow Melt Sys overcurrent protection LS 1 $2,732.80 $2,732.80 23 Crushed Surfacing Base Course(south berm) TN 5 $22.00 $110.00 25a Access Ctri Sys,keyed overide switch LS 1 $358.40 $358.40 25b Access Ctrl Sys,move antenna to face street LS 1 $280.00 $280.00 37a Gate-Laser Sensor Add LS 1 $585.76 $585.76 37b Gate-1/2 cost to modify bottom rail LS 1 $346.64 $346.64 TAX 8.7%SALES TAX $749.38 Total Amount of this Change Order: $9,362.98 SUBSTANTIAL COMPLETION Original Date: 3124/2014 Prior to this Change Order. 8/28/2014 Including this Change Order 9/5/2014 Original Working Days: 110 Working Days Added by this CO: 0 Working Days including this CO: 115 THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE: ORIGINAL TOTAL CONTRACT AMOUNT $ $750,865.90 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ $107,009.17 TOTAL CONTRACT PRICE PRIOR TO THIS CHANGE ORDER $ $857,875.07 NET THIS CHANGE ORDER - .._»� ~~- $9,362.98 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER . $ $867,238.06 CONTRACTOR ACCEPTANCE: / �! DATE: /2`(Z The contractor hereby accepts this ent acid the terms of the original contract for all work performed. RECOMMENDED BY: /, .a.."./LA.[.,ep DATE:. kr,DEC Zo ii- Project Manager APPROVED BY: _1/,�s,..r . . DATE: /Z`/7//`� ric ,fhublic Works Director APPROVED BY: � A JL" DATE: C It/ Mire ,City Manager ATTACHMENTS: cty- LMh't"s5 QV44-£S Distribution: ORIGINALS TO: City of Spokane Valley Clerk's Office,Contractor COPIES TO: PW Project File,Finance dept I1- - oyy DL( Z26 Thornton and Sons Inc \ Estimate PO Box 2505 t" Spokane WA 99220 509-487-5859 k Date Estimate# ta" LC-1 10/20/2014 291 THORNTON & SONSF Electrical Contractors License#THORNSI891BQ General Contractors License#THORNSI875DO S&L UNDERGROUND INC Jobsite Address PO BOX 1952 Spokane Valley Decant Facility BONNERS FERRY ID 83805 12116 E.Montgomery Dr. Spokane Valley, WA 99206 Job Name Terms CO#2 WARM ZONE BREAKER BOX As per contract Description Qty Amount Total Change Order to perform work as required to correct Overcurrent Protection discrepancy between sheet 35 of 39 and National Electrical Code. 1. Delete from C&W schedule Note P8,P9,and P10. 1 0.00 0.00T 2. Replace Note P10 with 1"PVC and(2)#12 THHW and(2)#10 THHW with(1)#10 1 0.00 0.00T THHW Ground. These conductors will land on breakers number 17,19 and 21,23 as shown on Panel Schedule. 3. Replace Note P9 with 2"PVC and(16)#8 THHW and(1)#8 THHW Ground. These 1 0.00 0.00T conductors will land on new breakers in control box listed below. 4. Provide and install Control Panel supplied by Control Freek. Control Panel shop drawing 1 2,440.00 2,440.00T provided by CSV and to be built to shop drawing specs. Labor-8 hrs X$115.00=$920.00 Control Freek breaker Cabinet= $1,200.00 4. (764, r0. �Kts Misc fastners,conduit,&wire=$320.00 292. 4:2132330 ACCEPTANCE OF TERMS Subtotal ESTIMATE IS GOOD FOR 20 DAYS. THE ABOVE PRICES,SPECIFICATIONS,AND CONDITIONS ARE SATISFACTORY AND HEREBY ACCEPTED. I AUTHORIZE YOU TO DO THE WORK AS SPECIFIED. PAYMENTS TERMS WILL BE OUTLINED AT TIME Sales Tax(8.7%) OF CONTRACT SIGNING. ACCOUNTS 30 DAYS PAST DUE ARE SUBJECT TO A SERVICE CHAGE OF 1.5%PER MONTH. Total Signature Page 1 WE ACCEPT VISA,MASTER CARD,AND DISCOVER CARD. Thornton and Sons Inc. rye., INVOICE PO Box 2505 Spokane WA 99220 j l is Invoice Date 10/24/2014 509-487-5859 �VO • Invoice 1015 THORNTON & SONS: ELECTRICAL CONTRACTORS Bill To --"-at---_--. EST 1984 —".-.-Y"- 1,091437.5859 I lhomlonendwns.Com I in,oethonstonand,ons.om S&L UNDERGROUND INC PO BOX 1952 BONKERS FERRY ID 83805 Electrical Contractors License#THORNSI891BQ General Contractors License#THORNSI875D0 Project P.O.No. Terms Spokane Vallet Decant 2647 As per contract Date Item Description Quantity Rate Amount 10/24/2014 Monthly billing for Spokane Valley Decant Facility 121 16 E. Montgomery Drive Spokane WA 99216- G FST� �i X29 COMMER... Change order#2 Warm Zone Breaker -.1-.snn ZZ� - 1 2,440.00 2,440.00T COMMER..: Change order#3 Knox switch 1:Keys 1 320.00 OT 4 2%d4) COMMER... Change order#S Antenna 1 250.00 250.00T 1f ,40 ( � 2e. _tem ZS� Subtotal $3.010.00 VISA,MASTERCARD, &DISCOVER ACCEPTED Sales Tax(8.7%) $261.87 Thank you for your business. Total 53,271.87 Payments/Credits $0.00 Balance Due $3,271.87 • Quiet Waters Construction Quotation Access Control DATE August 25, 2014 P.O. Box 9404 Quotation# SC9513.0/O Spokane, WA. 99209-9404 Customer ID Phone(509)328-4432 Fax(509)327-2600 Quotation valid until: September 4,2014 Bill To: Ship To: Slunder Spokane County Decant Fac Comments or special instructions: Change Order Quote Requested Fu nish And Install The Following AMOUNT Miller Edge IG2-K10 Battery Powered Photo Optic System $ 523.00 TOTAL $ 523.00 If you have any questions concerning this quotation, contact Rick Rail, 509-939-7370 Quietwatersca.msn.com THANK YOU FOR YOUR BUSINESS! +(2 c43 Addl4V1 = Irk,76 t61 ,•Wo • Art Jenkins From: Art Jenkins Sent: Thursday,July 24, 2014 12:17 PM To: Shem Cel (shem@slunder.com) Cc: Steve Kingsley; Nathan (nathan@slunder.com); Eric Guth;Andy@thorntonandsons.com Subject: SVR Decant- Electrical Items A/B - new box and conduit for Snow Melt System on east side of project Shem— KPFF has informally proposed a 5-way split to share costs on Electrical Items A& B,with total costs for this change not exceeding$7,000. The proposed share would be split as follows: [ 4o%toconsLfl (a C i, 7000 = zoo • 20%to S&L Underground }—'2-0%-to-the-eleEtr-icalsub_contr_a_ctor Thornton and Sons • 20%to the City of Spokane Valley(subject to internal City approval process) It is my understanding that the electrical subcontractor,Thornton and Sons was in contact with our consultants and seemed agreeable to this compromise. Please confirm that this arrangement will work for S&L Underground and your sub-contractor Thornton and Sons. Once I have your approval,we will work on formalizing this arrangement. Thanks, ART JENKINS, PE, CSM City of Spokane Valley-Public Works Department-Stormwater Utility 11707 E Sprague,Ste 106,Spokane Valley,WA 99206 Desk: 509-720-5018;fax: 509-688-0261; Email: aienkinsCWspokanevallev.org 1 Art Jenkins LTA 3-4 to From: John Hayden <john@idahofence.com> Sent: Thursday, September 25, 2014 1:08 PM To: Art Jenkins; 'Nathan'; 'Shem Cel' Cc: 'Blegen, Robert'; 'Humphreys, Russ' Subject: RE: 18 SEP 14 Walkthrough List.pdf Categories: Calls We will have this completed early next week. Thanks Original Message From:Art Jenkins [mailto:ajenkins@spokanevalley.org] Sent:Thursday,September 25, 2014 12:55 PM To: 'Nathan'; 'Shem Cel' Cc: 'Blegen, Robert'; 'Humphreys, Russ';John Hayden Subject: RE: 18 SEP 14 Walkthrough List.pdf Please proceed to modify the bottom of the gate to get the 6-inch minimum clearance at all positions and locations at the bottom of gate,with 12-inch minimum clearance at full closed position. We will process this as a change order and are prepared to share in up to half of the$619+OH&markup cost with the Contractor for this modification. Since we did not have the full 12-inch minimum clearance at closed position either,we expect that this requirement will be remedied with the proposed modification. Thanks, Art Jenkins, PE,CSM »»»»»»»»»»»»»»»»»»»»»»»»»»»»»»» >>>>>>» »»»»»»»»»»»»»»» City of Spokane Valley- Public Works Department-Stormwater Utility 11707 E Sprague,Ste 106,Spokane Valley,WA 99206 Desk: 509-720-5018;fax: 509-688-0261; Email: ajenkins@spokanevalley.org Original Message From:John Hayden [mailto:john@idahofence.com] Sent:Thursday,September 25,2014 12:23 PM To: 'Humphreys, Russ' Cc: 'Nathan';Art Jenkins; 'Blegen, Robert'; 'Shem Cel' Subject: RE: 18 SEP 14 Walkthrough List.pdf To modify the bottom of the fence is approximately$619.00, to remove the existing hinges(grind off) re-align and re- weld the hinges and fabricate the attachment for the gate operator,approximately$892.00 Original Message From: Humphreys, Russ [mailto:HumphrR@wsdot.wa.gov] Sent:Thursday,September 25,2014 12:15 PM To:John Hayden Cc: 'Nathan';Art Jenkins; Blegen, Robert; 'Shem Cel' Subject: Re: 18 SEP 14 Walkthrough List.pdf OK. I'm open to solution to make the 6"clearance when open. I'm OK with gate being higher than the fence.What is the difference to modify the gate bottom versus the alignment point issue. Sent from my Verizon Wireless 4G LTE DROID John Hayden<john@idahofence.com>wrote: You can do that as well, but the top of the gate will not be in alignment with the top of the fence. Also,to do as per your suggestion,the gate operator will need to be re-aligned adding additional cost. Original Message From: Humphreys, Russ [mailto:HumphrR@wsdot.wa.gov] Sent:Thursday, September 25, 2014 12:08 PM To: Nathan Cc:Art Jenkins; Blegen, Robert;Shem Cel;John Haden Subject: Re: 18 SEP 14 Walkthrough List.pdf I think a better solution was to adjust the hinge points on the gate like we talked on site. It would be less expensive to lower the gate hinge points,thus raising the gate on the gate post. Sent from my Verizon Wireless 4G LTE DROID Nathan<nathan@slunder.com>wrote: Do we need to cut the bottom of the bottom of the gate on an angle or raise the entire thing 5 inches? I am thinking of the top alinement on both ends. Sent from my iPhone On Sep 24, 2014,at 3:30 PM, "Humphreys, Russ" <HumphrR@wsdot.wa.gov<mailto:HumphrR@wsdot.wa.gov>>wrote: Please adjust as we spoke on site. Please provide 6" clear when the gate is fully opened. From: Art Jenkins [mailto:ajenkins@spokanevalley.org] Sent:Wednesday,September 24, 2014 3:30 PM To: Nathan; Humphreys, Russ Cc: Blegen, Robert;Shem Cel Subject: RE: 18 SEP 14 Walkthrough List.pdf 2 I'm getting about an 1-1/4 inches on my measure today with the gate fully open 90-degrees, 11%inches in the closed position. From: Nathan [mailto:nathan@slunder.com] Sent:Wednesday,September 24,2014 12:27 PM To: Humphreys, Russ Cc:Art Jenkins; Blegen, Robert;Shem Cel Subject: Re: 18 SEP 14 Walkthrough List.pdf It was 1 1/2"when I saw it at the last walk through. Sent from my iPhone On Sep 24, 2014, at 11:50 AM, "Humphreys, Russ" <HumphrR@wsdot.wa.gov<mailto:HumphrR@wsdot.wa.gov>>wrote: What is the dimension from the asphalt to the bottom of the gate in the full open position? From:Art Jenkins [mailto:ajenkins@spokanevalley.org] Sent:Wednesday,September 24, 2014 11:49 AM To: Nathan Cc: Humphreys, Russ; Blegen, Robert;Shem Cel Subject: RE: 18 SEP 14 Walkthrough List.pdf Yes-it looks higher today when I opened it and wasn't dragging on the upper end asphalt. The gate guys must have fine-tuned and adjusted the gate? Let me get back to you on whether this will be acceptable or not. Thanks, Art J. From: Nathan [mailto:nathan@slunder.com] Sent:Tuesday,September 23, 2014 3:23 PM To:Art Jenkins Cc: Russ Humphreys; Robert Blegen; Shem Cel Subject: Fwd: 18 SEP 14 Walkthrough List.pdf Shem measured the gate in the closed position. It is 11 1/4"from the pavement at the closest place.What would be the best thing to do? Sent from my iPhone Begin forwarded message: From: "John Hayden"<john@idahofence.com<mailto:john@idahofence.com>> Date: September 23,2014 at 2:51:00 PM PDT To: "'Nathan' <nathan@slunder.com<mailto:nathan@slunder.com>> Subject: RE: 18 SEP 14 Walkthrough List.pdf Nathan, is the city aware the gate is already approximately 12'off the ground in the close position? Original Message 3 From: Nathan [mailto:nathan@slunder.com] Sent:Tuesday,September 23, 2014 10:17 AM To:John Hayden Subject: Re: 18 SEP 14 Walkthrough List.pdf Please let me know the cost before we change the gate.Thanks Sent from my iPhone On Sep 23, 2014,at 5:10 AM, "John Hayden" <john@idahofence.com<mailto:john@idahofence.com>>wrote: Nathan, If we raise the gate, I think it would look best if we also cut the gate down in height. What do you think? Original Message From: Nathan [mailto:nathan@slunder.com] Sent: Monday,September 22,2014 7:45 PM To:John Hayden Subject: Re: 18 SEP 14 Walkthrough List.pdf What will it cost to raise the gate? Sent from my iPhone On Sep 22, 2014,at 12:37 PM, "John Hayden" <john@idahofence.com<mailto:john@idahofence.com>>wrote: It will be a change order to raise that gate. All other items we will take care of. Original Message From: Nathan [mailto:nathan@slunder.com] Sent: Monday,September 22,2014 12:35 PM To:John Haden; qwconst@gmail.com<mailto:qwconst@gmail.com> Subject: 18 SEP 14 Walkthrough List.pdf Please look this over and give me a call.Thanks Nathan.208 6101866 4 12/17/2014 7:13 AM SVR Decant Facility - Electrical Issue Schedule Item Issue Description Construction Status No. Resolution Currently with Status Est. Cost (excudes tax) A Snow Melt System Cable Length Electrical Contractor ordered standard lead length (20 -feet), sheet E1.0 calls for extra length to fit layout. constructed completed $7,000 (City share $1,400, Consultants $2,800) 8 Snow Melt System Conduit Size Cold leads provided by the manufactuer were 5/8 -Inch diameter, Sheet E1.0 calls for (2) leads to go through 1 -inch diameter conduit (see conduit tag P7) see A. - C Snow Melt Overcurrent Protection LNI written correction for over current protection for the snow melt system Additional work Completed completed $2,440.00 D Avista Meter Gear Move (15 -foot Clearance) Move the Avista CT/KWH Meter Rack from where placed by Electrical Contractor to keep 15 to 16 -foot minimum clearance as shown on sheet C6.0 and Sheet E1.1.- completed completed no added cost to City E Casing pipe for future bldg conduit Determined to extend quantities to run 12 -inch PVC as a casing pipe for future conduit run(s) for projected Phase 3 building under new drive approach, north of the gate loop. Constructed - completed City cost $1,560 F Move West -center S1 stand 4' to east, closer to new fence There was a questioned descrepancy between sheet C3.0 and E1.1 on placement of fence which led to foundation location off by 4 feet to the west. It appears that the fence line, however, was partially covered by a conduit line shown on drawing E1.1. All other drawings show the fence and the contractor should have reviewed other drawings or used scale on plan E1.1 to determine actual plan location of the S1 pole. contractor moved 7/21/2014 - completed no added cost to City G Gate Hinge approval Larger hinges required - no change in cost installed - completed no added cost to City H Gate Laser -eye sensor Installer of gate says we need this to meet gate code. installed - completed $523.00 I 51- 25 vs 30 -foot pole height Supplier will provide 30 -foot S2 light poles installed - completed no added cost to City Rigid versus Schedule 80 conduit between panel and control boxes Electrician requested using Schedule 80 conduit In lieu of steel as specified. Contractor directed to use steel on 7/23/2014 by City. installed - installed no added cost to City K Concrete testing of Light Pole Standard Bases Contractor did not notify City prior to pouring light pole standards onsite - need mix design used, may require core testing of concrete to verify strength. Light pole standards have been poured. City received batch tickets/mix design on 8/1/14. City determined that additional testing will not be required no added cost to City L Gate control system submittals Outstanding submittals from Electrical Sub for Gate control system Submitted to City on 24 JUL 2014 approved no added cost to City M Manual Keyed Switch for Gate Gate needs a manual overide switch outside fence, to be provided by City, per N5, Detail 2, Sheet E1.2. constructed - completed $320 N Access System Antenna Move Move one of the antennas on the Access Control System so that both point to Montgomery Drive. Antennas are shown Incorrect on sheets E1.2 and E1.3. moved - completed $250 #11,\ sookane Public Works Department Stormwater Utility 4 0 0 0 0.1 .flValley® 11707 E Sprague Ave Suite 106 • Spokane Valley WA 99206 509.921.1000 ♦ Fax: 509.688-0261 • cityhall@spokanevalley.org Change Order Memorandum Date: December 29, 2014 To: Eric Guth From: Art Jenkins, PE, CSM45.29 Re: Change Order#4 for Spokane Valley Regional Decant Facility Project#0173 Contract#14-009 Budget Account No. 403.000.173.594.31.63.00 S&L Underground, Contract 14-009 1. This final change order balances extensions/deletions of actual quantities used on the project. 2. It also resolves several issues to meet Electrical LNI, Fire Department, WSDOT, and OSHA requirements for the snow melt, gate, and access controls systems. . No additional time will be granted as a result of this change order. This work came in at or below our independent estimates. There are sufficient funds in the project budget to cover this change order. Original Contract Award approved by Council= $ 841,619.53 Change Orders#2 &#3 Cost= $ 16,255.54 Change Order#4 Cost= $ 9,362.98 Project Cost including Change Order#4 = $ 867,238.06 15% of Original Contract Award amount= $ 126,242.93 Max Public Works Director Contract authority= $ 75,000.00 • ($75,000 or 15%of original contract amount, whichever is less) Change Order Cost to date= $ 25,618.52 Remaining P.W. Director Contract Authority after CO#4 $ 49,381.48 cc: Finance Department Clerk's office