2012, 03-28 Permit: SW-12000002 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12-000002
Permit Issued Date:
03/27/2012
Expiration Date: 03/28/2012
Project Description:
Permit Type:
SEWER CONNECTION
SEWER
Primary Contact:
Applicant:
Address:
Phone:
Email:
STRAHL CONSTRUCTION INC
STRAHL CONSTRUCTION INC
3611 N CALSIPEL ST
SPOKANE, WA 99205
509-328-7919
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
Zoning:
422 S CALVIN LN
45232.1805
SP -118-79
MANOS VALLEY ESTATES PUD LT 5 BLK 2
(AFN# 5613158)
Water District: Vera
Irrigation District #15
Owner:
Address:
Phone:
Email:
CONTRACTOR INFORMATION.
General Contractor
BOB LONG
PO BOX 305
VALLEYFORD, WA 99036
509-951-1903
STRAHL CONSTRUCTION INC
3611 N CALISPEL ST
SPOKANE, WA 99205
509-328-7919
Fire District: Flre District 1
Land Area: 0.1231 acres l 5363-sgfL_.-- _-- -- _ ------__. __.--
^A
6icl-IZ-ZYO/Z11i
'.
1
DETAILS;
Class
Type
Quantity Unit Charge Value
SEWER
SEWER CONNECTION 1
FEE DETAIL;
Processing - Utilities
Utilities Permit
$125.00 $125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FORA 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 03/27/2012 10:01:57
Printed by: IIS APPPOOLVISP.NET v4.0
TOOPI 'DOTS 00 HNVHOdS 86TLLLi' 'Ng Lo:TT ZTOZ/L2/£0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12-000002 03/27/2012
Expiration Date: 03/28/2012
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 03/27/2012 10:01:57
Printed by: IIS APPPOOLWSP.NET v4.0