2015, 04-03 Permit: SW-15000266 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -15000266 Permit Issued Date: 04/03/2015
Expiration Date: 04/03/2016
Project Description: SEWER
Project Name: SUTTERS PH 3
Primary Contact: C H D INC
Phone: 509-994-3972
Applicant: C H D INC
Address: 5025 N ARGONNE RD, SUITE 1
SPOKANE, WA 99212
Phone: 509-994-3972
Email: WES.CROSBY@COMCAST.NET
SITE INFORMATION:
Site Address:
Parcel Number:
903 S BEST RD
45233.0505
Assessor's Description: VERA TALLY HO B148 L5B1
Inspection Area: : (509)-477-3675
Owner:
Address:
Phone:
Email:
FEDERAL HOME LOAN MORTGAGE
CORP
1000 TECHNOLOGY DR MS 420
O'FALLON, TX 63368-2240
Water District: Vera Irrigation District #15 Fire District: Spokane Valley Fire
Zoning: Land Area: 10959 Square Feet
CONTRACTOR INFORMATION:
CHDIN**126LC, Exp. 08/23/2016
C H D INC
5025 N ARGONNE RD, SUITE 1 SPOKANE, WA
99212
509-994-3972
WES.CROSBY@COMCAST.N ET
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$27.12
$125.00
$152.12
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
SVRP Aquifer Boundary: Water Purveyor ability to serve statement required. If unable to serve, ?mitigation certificate? (use of private well)
from DOE prior to permit issuance.
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed: 04/03/2015 09:54:48 Project Coordinator: Susan Clark
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -15000266 Permit Issued Date: 04/03/2015
Expiration Date: 04/03/2016
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 04/03/2015 09:54:48 Project Coordinator: Susan Clark