14-039.05 Max J Kuney: Sullivan West Bridge Ph 2 SpÔ1ane.00
Valley.
CHANGE ORDER NO: 5
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-039
PROJECT: Phase 2-Sullivan Road West Bridge Replacement Project CONTRACT DATE: 8/8/2014
PRIME CONTRACTOR: Max J. Kuney Company CIP NO: 0155
DESCRIPTION OF CHANGES
This Change Order pertains to: All Bid Schedules
The Local Agency Disadvantaged Business Enterprise Utilization Certification (Certification), which was submitted as part of
Max J. Kuney's bid proposal and deemed a part of the Contract, is amended as shown in Change Order No. 5-
Attachment A.
Item No. Description Unit Quantity Unit Price Total
CO-5.1(A) DBE Subcontractor Substitution LS 1 0.00 $ 0.00
8.7% Sales Tax(applicable only to Bid Schedules C,D,and E) $ NA
Total Amount of this Chan•e Order incl.Tax : $ 0.00
PHYSICAL COMPLETION
Original Contract Working Days: 484 Revision By This Change Order: 0
Revisions by Prior Change Orders: 10 Total Revised Contract Working Days: 494
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 12,307,560.31
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#4) $ 59,362.36
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 12,366,922.67
NET THIS CHANGE ORDER $ 0.00
TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 12,366,922.67
CONTRACTOR ACCEPTANCE: DATE: (j2//5
The contractor hereby accepts this a justment nder the to of ection 1-04.4 of the original contract.
RECOMMENDED BY: 1 a J DATE:
/2- 2D
Proj anager
APPROVED BY: G 4 .� '��1` DATE: L3 /,ç
Public Works Director
APPROVED BY: PA DATE:
City Manager
ATTACHMENTS:
Change Order No. 5-Attachment A
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor, PW Project File, Project Inspector, Finance Department,WSDOT ER Local Programs
COSY Form 9/5/2014