15-002.01 Inland Asphalt: Sullivan Street Preservation 6-002.0
SFo`kaxie
••00Va11[eyt
CHANGE ORDER NO: 1
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 15-002
PROJECT: Sullivan Rd St Preservation CONTRACT DATE: 5115/2015
PRIME CONTRACTOR: Inland Asphalt Company CIP NO: 188
DESCRIPTION OF CHANGES
This Change Order pertains to Bid Schedule: A
The existing diameter of conduit sweeps accessing existing signal junction boxes is not large enough for the new vehicle
detection loop feeds. This Change Order pays for installation of new sweeps and associated curb and sidewalk work at the
following Sullivan Rd locations:34+00 RT,42+75 RT and 44+95 RT. The sweep and JBox adjustment work will be paid by
Force Account procedures.
item No. Description Unit Quantity Unit Price Total
CO-1.1 Remove Cement Concrete Curb&Gutter LF 10 $ 11.45 $ 114.50
CO-1.2 Remove Cement Concrete Sidewalk&Drwy Appr. SY 7 $ 12.45 $ 87.15
CO-1.3 Cement Concrete Curb and Gutter LF 10 $ 18.00 $ 180.00
CO-1.4 Cement Concrete Sidewalk SY 7 $ 31.00 $ 217.00
CO-1.5 Force Account Sweep install and J Box adjustment CALC 1 $ $ 2A84.73
Total Amount of this Change Order(incl.Tax): $ 3,083.38
PHYSICAL COMPLETION
Original Contract Working Days:_45 Revision By This Change Order:
Revisions by Prior Change Orders: 0 _ Total Revised Contract Working Days: 45
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 894,884.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT $ 0.00
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER -__ $ 894.88400
NET THIS CHANGE ORDER .... $ 3,083.38
TOTAL CONTRACT AMOUNT INCLU NG THIS CHANGE ORDER ----�~-.,..- —~ $ 897,967 38
'it)
CONTRACTOR ACCEPTANCE: y2,405—The contractor hereby accepts this adjustment un. �3'-rms of Section 1-04.4 of the original contract.
RECOMMENDED BY: G�i�'''9? T DATE: 6 •2g-/,j
Project Manager
APPROVED BY: J � DATE: C /2 y//
,// Public Works Director
APPROVED BY: /04 DATE:
City Manager
ATTACHMENTS: Plan Sheets 14&15.revised 6-23-15 showing CO-1 work
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File.Project Inspector.Finance Department
COSY Form 9?5(2014