15-002.02 Inland Asphalt: Sullivan Street Preservation (S- 002. 02_,
Spokane
� ya
CHANGE ORDER NO: 2
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 15-002
PROJECT: Sullivan Rd St Preservation CONTRACT DATE: 5/15/2015
PRIME CONTRACTOR: Inland Asphalt Company CIP NO: 188
DESCRIPTION OF CHANGES
This Change Order pertains to Bid Schedule: A
This Change Order pays for modifications to Temporary Traffic Control Stage 3A shown on the attached revised Plan Sheet
23. The work consists of installing 21 tubular markers at the SB Sullivan approach to Broadway. The devices will reduce
driver confusion during this traffic control stage and increase traffic flow through the intersection.
Item No. Description Unit Quantity Unit Price Total
CO-2.1 Force Account Temp Traffic Control LS 1 $ 310.87 $ 310.87
Stage 3A Plan Modifications
Total Amount of this Change Order(incl.Tax): $ 310.87
PHYSICAL COMPLETION
Original Contract Working Days: 45 Revision By This Change Order.. 0
Revisions by Prior Change Orders: 0 Total Revised Contract Working Days: 45
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 894,884.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO# 1) $ 3,083.38
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 897,967.38
NET THIS CHANGE ORDER $ 310.87
TOTAL CONTRACT AMOUNT INCLUD T IS C . ORDER $ 898,278.25
1!i•_ /
CONTRACTOR ACCEPTANCE: �, DATE: 62/24/5—
The contractor hereby accepts this adjustment un•e e te,Is of Section 1-04.4 of the original contract.
RECOMMENDED BY: DATE: to-23'/S'
/ir -rojectMana er
APPROVED BY: I �` . 4-2�� DATE: 6/Z.0S
ff Public Works Director/
APPROVED BY: DATE:
City Manager
ATTACHMENTS: Plan Sheet 23,revised 6-19-15 showing tubular marker locations.
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department
COSY Form 5!512014