2012, 05-09 Permit: SW-12001303 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
r.
Permit Issued Date:
Application Number: SW -12001303 05/09/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: GOBERS LLC
Project Name: UNIVERSITY PLACE U.L.I.D. Applicant: GOBERS LLC
Permit Type: SEWER Address: 11215 E TRENT AVE
SPOKANE, WA 99206
Phone: (509)924-5372
Email:
SITE INFORMATION:
Site Address: 9723 E CROSSBOW CTOwner: SATY, DAVID
Parcel Number: 45203.1213 Address: 9723 E CROSSBOW CRT
SPOKANE, WA 99206-3437
Subdivision: SHERWOOD FOREST Phone:
Assessor's Description: SHERWOOD FOREST L13 B2 Email:
Inspection Area:
Water District: Spokane Fire District: Fire District 1
County Water District #3
Zoning: Land Area: 0.527 acres / 22955.8 sgft.
CONTRACTOR INFORMATION:
General Contractor
GOBERL"8991_7
`GOBER'S, LLC
11215 E. TRENT AVE.
SPOKANE, WA 99206
509-924-5372
DETAILS:
Class Type Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
$125.00
FEE DETAIL:
Processing - Utilities $25.94
Utilities Permit $125.00
Total Fee: $150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY. __________________________
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 05/09/2012 14:32:35 Printed by: IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001303 05/09/2012
Expiration Date:
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
----------------------------------------------------
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
----------=-----------------------------------------
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
—------------—--———————————————————————————--— — — — — — —