Resolution 15-005 Adopts 2016-2021 TIP CITY OF SPOKANE VALLEY
SPOKANE COUNTY,WASHINGTON
RESOLUTION NO. 15-005
A RESOLUTION OF THE CITY OF SPOKANE VALLEY, SPOKANE COUNTY,
WASHINGTON, ADOPTING THE 2016-2021 SIX-YEAR TRANSPORTATION
IMPROVEMENT PROGRAM FOR THE CITY OF SPOKANE VALLEY, AND OTHER
MATTERS RELATED THERETO.
WHEREAS, to provide for the proper and necessary development of the street system within the
City of Spokane Valley, the City shall, as required by State law, develop and adopt annually a Six-Year
Transportation Improvement Program ("Six-Year TIP") with such program acting as a guide for the
coordinated development of the City's transportation system;and
WHEREAS, the Six-Year TIP of the City shall specifically set forth those projects and programs
of both City and regional significance that benefit the transportation system and promote public safety
and efficient vehicle movements; and
WHEREAS, the Six-Year TIP shall be consistent with the City Comprehensive Plan and be
adopted following one or more public hearings before the City Council; and
WHEREAS, a draft copy of the Six-Year TIP was submitted to the Washington State Department
of Commerce and has been reviewed and approved prior to the scheduled adoption of the TIP in
accordance with RCW 36.70A.106; and
WHEREAS, the City Council conducted a public hearing on June 9, 2015, for the purpose of
inviting and receiving public comment on the proposed Six-Year TIP.
NOW THEREFORE,be it resolved by the City Council of the City of Spokane Valley, Spokane
County, Washington, as follows:
The City Council hereby adopts the attached Six-Year TIP for the City of Spokane Valley
for the purpose of guiding the design, development and construction of local and regional
transportation improvements for the years 2016 through 2021. The City Clerk is directed
to file the 2016-2021 Six-Year Transportation Improvement Program with the
Washington State Secretary of Transportation before July 1. The TIP shall be reviewed
at least annually for the purpose of determining the work to be accomplished under the
program and the City transportation requirements.
Adopted this 23`d day of June,2015. City of Spokane Valley
lean Grafos, Mayor /+
AT S .
11/'1A l9Dz9e9vi
Christine Bainbridge, City Clerk
Approved as to Form:
Offic f the Ci /orney
Resolution 15-005,Adopting Six-Year TIP
SiOkane
�sUalley
City of Spokane Valley
Public Works Department
2016 - 2021 Six Year
Transportation Improvement Program
June 23, 2015
Resolution No. 15-005
City of Spokane Valley
Department of Public Works
2016 — 2021 Six-Year `i
pokane
Transportation Improvement Program .Valley
G!ossary & Abbreviations
Funding Sources:
• ARRA American Recovery & Reinvestment Act
• BR Bridge Replacement Program Funding Status:
• City City Funds • S Project Funding is Secured
• CDBG Community Development Block Grant • P Project Funding is Planned. The Most
• CMAQ Congestion Management/Air Quality Probable Funding Sources have been
• Developers Private Developer Funds Identified.
• EECBG Energy Efficiency and Conservation Block Grant
• FHWA Federal Highway Administration Project Phases:
• FMSIB Freight Mobility Strategic Investment Program • PE Preliminary Engineering
• HSIP Highway Safety Improvement Program • RW Right-of-Way
• HUD Housing & Urban Development • CN Construction
• REET Real Estate Excise Tax
• Other Fed Misc. Federal Funding Sources Construction Type:
• Other RR Railroad Funding • PCC Portland Cement Concrete
• Other State Misc. State Funding Sources • HMA Hot Mix Asphalt
• SP TIB Sidewalk Program • ITS Intelligent Transportation System
• SRTS Safe Routes to School (Integrated Traffic Signal Control Systems)
• SW City Stormwater Funds • S/W Sidewalk
• STA Spokane Transit Authority
• STP(E) Surface Transportation Program (Enhancement)
• STP(U) Surface Transportation Program (Urban)
• TA Transportation Alternatives Street Functional Classifications:
• TIB Transportation Improvement Board Urban:
• UAP TIB Urban Arterial Program • 14 Principal Arterial
• UCP TIB Urban Corridor Program • 16 Minor Arterial
• WSDOT Washington Department of Transportation • 17 Collector Arterial
• WTSC Washington Traffic Safety Commission • 19 Local Access
• WUTC Washington Utilities &Transportation Commission
Spoka`nTe 2016 - 2021
Six-Year Transportation improvement Program
/alley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
I Sullivan Road West Bridge 0.08 0 0 5,064 5,064 BR 1,711 1,711
S City 536 536
FMSIB 600 600
Reconstruct and widen west(southbound)bridge Other 1,167 1,167
Fed
TIB 1,050 1,050
Recv'd FMSIB,BR&TIB grants;City Project#0155
Project Total 5,064 5,064
2 Mission Ave.-Flora Rd.to Barker Rd. (PE/RW) 1 155 160 0 316 City 43 43
S STP(U) 273 273
Reconstruct with curb,sidewalks,bike lanes and stormwater facilities;
PE&RW Funding Secured,(SRTC#09-01) City Project#0123,
Project Total 316 316
3 Citywide Reflective Signal Backplates o 0 0 72 72 City
S HSIP 72 72
New Traffic Signal Backplates at 10 City Intersections
2015-2017 HSIP Grant Award
Project Total 72 72
4 McDonald Rd ROAD DIET, 16th to Mission 2 28 0 545 574 HSIP 571 571
S City 3 3
Bike Lanes,traffic signal modifications,new ADA sidewalk ramps at traffic signals.
Project Total 574 574
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 1
2016 - 2021
Spokane Six-Year TransporA -,M-.. 'r-r rovement Program
Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
5 Seth Woodard Elem Sidewalk Imp, Mission & 0.25 42 0 319 361 City 30 30
p Park CDBG 331 331
Construct ADA sidewalk&curb ramps on the South side of Mission from Lily to Park,and along Park north along the
school and E Spokane Grange frontage
Project Total 361 361
6 Sprague/Barker Intersection Improvements 0 39 12 422 472 City 12 211 223
P DEV 38 211 249
Intersection improvements to improve capacity
Developer+City Partnership
Project Total 50 422 472
7 2016 Street Preservation Project o 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
8 Appleway-Park to Dishman Mica Preservation 1.1 83 0 1,071 1,154 City 11 145 156
S STP(U) 72 926 998
Grind and Overlay,ADA Upgrades
Funded with STP(U)funds.
Project Total 83 1,071 1,154
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an,
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 2
2016 - 2021
Spokane Six-Year Transpor"--.tion -orovement Program
Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
9 Appleway Shared Use Path-Pines Rd to 1 146 0 1,885 2,030 City 31 405 436
s Evergreen Rd STP(U) 69 901 970
TAP 45 579 624
Construct Shared Use Pathway along abandoned RR R-O-W
Funded with STP(U)funds.
Project Total 145 1,885 2,030
10 Fancher/BNSF RR Overpass Joint Repair 0 29 0 172 201 City 201 201
p Project
Repair bridge expansion joints on RR overpass
Project Total 201 201
11 Maribeau Pkwy&Pine (SR-27)Traffic Signal 0.1 30 0 320 350 City 350 350
P
New Traffic Signal
Traffic Signal PE&CN,beginning 2016
Project Total 350 350
12 2017 Street Preservation Project 0 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 3
2016 - 2021
Spokane Six-Year Transpor-F- -. ,'-°:orovement Program
..••• •Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
13 Argonne-Broadway to Indiana 0.8 64 0 576 640 City 9 78 87
S STP(U) 55 498 553
Pavement Preservation-Grind and Overlay
Funded with STP(U)funds.
Project Total 64 576 640
14 Mission &Pines(SR-27) Intersection Imp 0.2 35 50 250 336 City 34 34
p Project HSIP 302 302
Intersection lane reconfiguration and ROW on East and West Approches on Mission
Project Total 336 336
15 Opportunity Elementary, SRTS (Bowdish Road) 0.25 90 6 404 500 City 12 56 68
P TAP 79 353 432
Construct sidewalk along the east side of Bowdish from 8th to 12th,and along the south side of 11th from Bowdish to
Wilbur
TA Grant Application for 2018-2020 grant cycle
Project Total 91 409 500
16 Sullivan/Euclid Concrete Intersection (RW/CN) 0 0 26 2,082 2,108 City 421 421
P TIB 1,687 1,687
Reconstruct intersection in concrete pavement
PE Obligated 9/2010
Project Total 2,108 2,108
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an,
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 4
2016 - 2021
Sokane���'
O Six-Year Transportatilon Improvement Program
Valley Dollars
n Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
17 North Sullivan ITS Project 1.75 105 0 809 914 City 14 109 123
S CMAQ 91 700 791
Extend ITS conduit and controls along Sullivan Corridor
CMAQ Funded
Project Total 105 809 914
18 Sullivan-Trent(SR-290)to Wellesley Corridor 0.3 90 50 600 740 City 12 62 74
p Lighting HSIP 104 562 666
Street lighting,ROW
Project Total 116 624 740
19 Sullivan-Wellesley Intersection Imp Project 0.25 198 110 1,062 1,368 City 34 150 184
P CMAQ 218 966 1,184
Traffic Signal or Roundabout
Project Total 252 1,116 1,368
20 2018 Street Preservation Project o 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an,
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 5
�,,,(N 2016 - 2021
Spokane Six-Year Transpnrtation Improvement Program
Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RIP/ CN Total Sources 2016 2017 2018 2019 2020 2021 Total
21 Appleway Trail-Evergreen to Sullivan 1 164 0 1,481 1,645 City 22 200 222
P CMAQ 142 1,281 1,423
Construct Shared Use Pathway along abandoned Railroad Right-of-Way
Project Total 164 1,481 1,645
22 Appleway Trail-University Rd.to Balfour Park 0.5 100 130 520 750 City 32 70 102
p TAP 198 450 648
Extend Shared Use pathway to Balfour Park
Project Total 230 520 750
23 Argonne Road Concrete Pavement-1-90 to 0.25 512 0 3,211 3,723 City 102 642 744
p Montgomery TIB 410 2,569 2,979
Reconstruct pavement in concrete;OCI Mullan to Knox 24,OCI Knox to Montgomery 35(2014 Rpt)
Project Total 512 3,211 3,723
24 Citywide Sidewalk Infill Project 1 140 30 830 1,000 City 152 848 1,000
P
Infill gaps in Sidewalks and add sidewalks to access completed portions of the Appleway Trail.
Project Total 152 848 1,000
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an,
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 6
2016 - 2021
Spokane Six-Year Transpora�—'., —provement Program
j Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
25 Evergreen Resurfacing-Mission Connector to 0.7 80 0 580 660 City 6 84 90
S Indiana STP(U) 34 536 570
Grind and inlay HMA,Bike Lane Positive Guidance thru the 1-90 EXIT 291-A
Project Total 40 620 660
26 Sprague-Sullivan to Corbin Preservation 0.85 177 0 1,593 1,770 City 24 215 239
S STP(U) 153 1,378 1,531
Pavement Preservation,ADA upgrade
Funded with STP(U)funds.
Project Total 177 1,593 1,770
27 2019 Street Preservation Project o 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
28 Broadway @ Argonne/Mullan Concrete 0 0 0 1,703 1,703 City 230 230
p Intersections(CN Only) STP(U) 1,473 1,473
Reconstruct intersections in concrete pavement
ROW Obligated 11/2013
Project Total 1,703 1,703
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,am
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 7
S,,,, x. 2016 - 2021
pokane
p Six-Year Transpr�. -'--' -�� � "����orovement Program
Val ley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
29 Broadway Improvement Project-Flora to 0 543 500 4,163 5,206 City 159 883 1,042
p Barker TIB 634 3,530 4,164
Extend Broadway arterial to Barker Rd,Realign Broadway connection east of Barker
3-Lane Urban Section
Project Total 793 4,413 5,206
30 Evergreen &Broadway ITS 2 206 80 1,584 1,870 City 36 217 253
P CMAQ 230 1,387 1,617
ITS along Broadway from Pines Rd(SR-27)to Evergreen,along Evergreen from Sprague to 16th Ave.
2018-2020 CMAQ Grant Application funding
Project Total 266 1,604 1,870
31 Mission Ave.-Flora Rd.to Barker Rd. (CN) 1 0 0 3,697 3,701 City 499 499
p TIB 1,601 1,601
STP(U) 1,601 1,601
Widen&Overlay with curb,sidewalks,bike lanes and stormwater facilities
Project Total 3,701 3,701
32 Park Road#2-Broadway to Indiana (RW&CN) 0.75 0 150 2,877 3,027 City 20 388 408
p STP(U) 130 2,489 2,619
Reconstruct to a 3-lane section with curb,sidewalks,bike lanes and stormwater facilities
PE Funding 6/2009
Project Total 150 2,877 3,027
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 8
'-1 2016 - 2021
Spokane Six-Year Transpor'•-,- ° - '3rovement Program
.800.00 Valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
33 Pines(SR27)/BNSF Underpass-(PE only) 0 3,000 0 0 3,002 City 128 128 256
P Other 1,298 1,298 2,596
Fed
Other- 75 75 150
RR
Railroad underpass at Pines(SR-27)/BNSF/Trent
Project Total 1,501 1,501 3,002
34 2020 Street Preservation Project 0 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
35 Appleway Trail-Sullivan to Corbin 1.33 200 0 2,200 2,400 City 27 297 324
P CMAQ 173 1,903 2,076
Shared Use Path along Old Milwaukee R/R ROW
Project Total 200 2,200 2,400
36 Barker Rd-Euclid to Flora Road 0.75 471 100 3,613 4,184 City 114 723 837
P TIB 457 2,890 3,347
Reconstruct Barker to 3-lane urban section
Project Total 571 3,613 4,184
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 9
2016 - 2021
Spokane Six-Year Transpor'—^'---: provement Program
j\alley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
37 Barker Rd Improvement Project-Appleway to I- 0.28 382 1,146 2,397 3,629 City 167 324 491
p 90 STP(U) 1,065 2,073 3,138
Widen and improve to 5-lane urban section,Roundabout @ Broadway,Realign east leg of Broadway
Project Total 1,232 2,397 3,629
38 Barker Rd Improvements-South City Limits to 0.81 326 25 2,502 2,854 City 46 340 386
p Appleway TIB 293 2,175 2,468
Widen and Improve roadway to 3-lane urban section
Project Total 339 2,515 2,854
39 2021 Street Preservation Project o 100 0 2,100 2,200 City 2,200 2,200
P
Pavement Preservation Projects: Fund 311
Ongoing,yearly
Project Total 2,200 2,200
40 Argonne Rd &I-90 IC Bridge Widening 0.1 800 0 0 800 City 160 160
p FMSIB 640 640
Widen Argonne Rd Bridge to 3 Lanes,SB. New 12' sidewalks.
Project Total 800 800
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an,
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 10
<,,,, 2016 - 2021
Spokane Six-Year Transpr :A9 n q7!provement Program
valley Dollars in Thousands
Funding
Project/Description/Current Status Length PE RW CN Total Sources 2016 2017 2018 2019 2020 2021 Total
41 Barker Rd Improvement Project-Spokane 0.53 378 25 0 403 City 52 52
p River to Euclid TIB 322 322
DEV 29 29
Reconstruct and widen to 3-lane urban section
Developer Funds Recd 6/2014,$29,500
Project Total 403 403
42 Barker Road I BNSF Grade Separation 0.5 1,538 450 0 1,988 City 308 308
p Other 180 180
Fed
Other 1,500 1,500
State
Construct Grade Separation at Barker/BNSF RR/Trent(SR290) Other-
RR
Other
Fed
FY09 Federal Earmark for$720K,20%of CN(up to$10M)received from FMSIB FMSIB
Project Total 1,988 1,988
Totals: 10,751 3,050 61,204 75,004 9,416 6,422 7,712 20,112 14,937 16,116 74,715
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 11
,„. • 2016 - 2021
>Milley
Six-Year Transportation Improvement Program
Six-Year Transportation Improvement Program Totals
Secured Projects Planned Projects Totals
Year Federal State Other City State Other City
2016 $3,980 $1,650 $0 $624 $6,254 $331 $0 $38 $2,793 $3,162 $4,311 $1,650 $38 $3,417 $9,416
2017 $1,072 $0 $0 $168 $1,240 $406 $1,687 $211 $2,878 $5,182 $1,478 $1,687 $211 $3,046 $6,422
2018 $2,865 $0 $0 $622 $3,487 $1,199 $410 $0 $2,616 $4,225 $4,064 $410 $0 $3,238 $7,712
2019 $1,914 $0 $0 $299 $2,213 $7,782 $4,804 $75 $5,238 $17,899 $9,696 $4,804 $75 $5,537 $20,112
2020 $0 $0 $0 $0 $0 $6,412 $4,280 $75 $4,170 $14,937 $6,412 $4,280 $75 $4,170 $14,937
2021 $0 $0 $0 $0 $0 $4,156 $7,527 $29 $4,404 $16,116 $4,156 $7,527 $29 $4,404 $16,116
Total $9,831 $1,650 $0 $1,713 $13,194 $20,286 $18,708 $428 $22,099 $61,521 $30,117 $20,358 $428 $23,812 $74,715
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,an.
are not intended by the City to be relied upon by property owners or developers in making development decisions.
6/24/2015 Page 1
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects wl No Currently Identified Local Match Within Existing Resources
Dollars in Thousands
Project Name Description Total Cost
Wellesley Realignment @ Realign connection of Wellesley to Barker Rd and $5,187
Barker/SR290 SR290,3-lane section,Part of Barker/BNSF
Grade Separation
Bowdish Road-16th to Sprague Sprague to 8th:Inlay&Enhancement;8th to $2,858
16th:Reconstruct as 2-lane section w/curb,
sidewalk,bike lanes and new stormwater facilities
Bowdish Road-24th to 16th Reconstruct Roadway as 2-lane section w/curb, $2,846
sidewalk and new stormwater facilities;
Bowdish Road-32nd to 24th Reconstruct Roadway as 2-lane section w/curb, $2,637
sidewalk and new stormwater facilities;
Bowdish Sidewalk-12th toi6th Construct Sidewalk along both sides of Bowdish $557
Park Road#2 Sidewalk Project- Construct sidewalk along one side of Park Road $143
Marietta Ave.to Buckeye Ave. and 160-ft gap on north side of Buckeye Ave east
of Park Road
Park Road/BNSF Grade Separation Reconstruct Park Road to separate the grades of $18,993
Park Road and the BNSF railroad tracks.
Pavement Management Program- Annual street preservation projects $11,664
Local Access
Pines(SR27)/BNSF Underpass Construct grade separation at Pines Rd(SR-27)/ $17,184
(RW,CN Only) Trent Ave(SR 290)/BNSF RR
Pines Corridor ITS-Sprague to 16th Traffic Signal Control System for Corridor $785
Sprague/Argonne-Mullan Concrete Reconstruct intersections in concrete pavement $2,342
Intersections
Sprague/Fancher Concrete Reconstruct Intersection in concrete pavement $1,572
Intersection
Sprague/Thierman Concrete Reconstruct intersection in concrete pavement $1,243
Intersection
Sprague/University Concrete Reconstruct intersection in concrete pavement. $1,660
Intersection
Sullivan/Kiernan Concrete Reconstruct Intersection in concrete pavement $1,423
Intersection
Sullivan/Marietta Concrete Reconstruct intersection in concrete pavement $1,493
Intersection
Sullivan Rd/BNSF Grade Upgrade and widen grade separation at $16,150
Separation Improvements Sullivan/BNSF/Trent(SR290)
Totals: $88,737
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 1 of 1
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Arterial Improvements
Project Name Description Start Year City Cost Total Cost
Mission Ave.-Flora Rd.to Barker Reconstruct with curb,sidewalks, 2016 $43 $316
Rd.(PE/RW) bike lanes and stormwater facilities;
Sullivan-Wellesley Intersection Imp Traffic Signal or Roundabout 2018 $184 $1,368
Project
Broadway Improvement Project- Extend Broadway arterial to Barker 2019 $1,042 $5,206
Flora to Barker Rd,Realign Broadway connection
east of Barker
Mission Ave.-Flora Rd.to Barker Widen&Overlay with curb, 2019 $499 $3,701
Rd.(CN) sidewalks.bike lanes and stormwater
facilities
Park Road#2-Broadway to Indiana Reconstruct to a 3-lane section with 2019 $408 $3,027
(RW&CN) curb,sidewalks,bike lanes and
stormwater facilities
Pines(SR27)/BNSF Underpass- Railroad underpass at Pines(SR-27) 2019 $256 $3,002
(PE only) /BNSF/Trent
Barker Rd-Euclid to Flora Road Reconstruct Barker to 3-lane urban 2020 $837 $4,184
section
Barker Rd Improvement Project- Widen and improve to 5-lane urban 2020 $491 $3,629
Appleway to 1-90 section,Roundabout @ Broadway,
Realign east leg of Broadway
Barker Rd Improvements-South City Widen and Improve roadway to 3- 2020 $386 $2,854
Limits to Appleway lane urban section
Barker Rd Improvement Project- Reconstruct and widen to 3-lane 2021 $52 $403
Spokane River to Euclid urban section
Total: $4,198 $27,690
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 1 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Bridge Projects
Project Name Description Start Year City Cost Total Cost
Sullivan Road West Bridge Reconstruct and widen west 2016 $536 $5,064
(southbound)bridge
Fancher/BNSF RR Overpass Joint Repair bridge expansion joints on RR 2016 $201 $201
Repair Project overpass
Argonne Rd&I-90 IC Bridge Widen Argonne Rd Bridge to 3 2021 $160 $800
Widening Lanes,SB. New 12' sidewalks.
Barker Road/BNSF Grade Construct Grade Separation at 2021 $308 $1,988
Separation Barker/BNSF RR/Trent(SR290)
Total: $1,205 $8,053
Congestion Improvements
Project Name Description Start Year City Cost Total Cost
Sprague/Barker Intersection Intersection improvements to improve 2016 $223 $472
Improvements capacity
Total: $223 $472
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 2 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Pedestrian/Bicycle Program
Project Name Description Start Year City Cost Total Cost
Seth Woodard Elem Sidewalk Imp, Construct ADA sidewalk&curb 2016 $30 $361
Mission&Park ramps on the South side of Mission
from Lily to Park,and along Park
north along the school and E
Spokane Grange frontage
Appleway Shared Use Path-Pines Construct Shared Use Pathway along 2016 $436 $2,030
Rd to Evergreen Rd abandoned RR R-O-W
Opportunity Elementary,SRTS Construct sidewalk along the east 2017 $68 $500
(Bowdish Road) side of Bowdish from 8th to 12th,and
along the south side of 11th from
Bowdish to Wilbur
Appleway Trail-Evergreen to Sullivan Construct Shared Use Pathway along 2018 $222 $1,645
abandoned Railroad Right-of-Way
Appleway Trail-University Rd.to Extend Shared Use pathway to 2018 $102 $750
Balfour Park Balfour Park
Citywide Sidewalk Infill Project Infill gaps in Sidewalks and add 2018 $1,000 $1,000
sidewalks to access completed
portions of the Appleway Trail.
Appleway Trail-Sullivan to Corbin Shared Use Path along Old 2020 $324 $2,400
Milwaukee R/R ROW
Total: $2,182 $8,686
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 3 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Safety Program
Project Name Description Start Year City Cost Total Cost
Citywide Reflective Signal Backplates New Traffic Signal Backplates at 10 2016 $0 $72
City Intersections
McDonald Rd ROAD DIET,16th to Bike Lanes,traffic signal 2016 $3 $574
Mission modifications,new ADA sidewalk
ramps at traffic signals.
Mission&Pines(SR-27)Intersection Intersection lane reconfiguration and 2017 $34 $336
Imp Project ROW on East and West Approches
on Mission
Sullivan-Trent(SR-290)to Wellesley Street lighting,ROW 2017 $74 $740
Corridor Lighting
Total: $111 $1,722
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 4 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Street Preservation Projects
Project Name Description Start Year City Cost Total Cost
2016 Street Preservation Project Pavement Preservation Projects: 2016 $2,200 $2,200
Fund 311
Appleway-Park to Dishman Mica Grind and Overlay,ADA Upgrades 2016 $156 $1,154
Preservation
2017 Street Preservation Project Pavement Preservation Projects: 2017 $2,200 $2,200
Fund 311
Argonne-Broadway to Indiana Pavement Preservation-Grind and 2017 $87 $640
Overlay
2018 Street Preservation Project Pavement Preservation Projects: 2018 $2,200 $2,200
Fund 311
Evergreen Resurfacing-Mission Grind and inlay HMA,Bike Lane 2018 $90 $660
Connector to Indiana Positive Guidance thru the 1-90 EXIT
291-A
Sprague-Sullivan to Corbin Pavement Preservation,ADA upgrade 2018 $239 $1,770
Preservation
2019 Street Preservation Project Pavement Preservation Projects: 2019 $2,200 $2,200
Fund 311
2020 Street Preservation Project Pavement Preservation Projects: 2020 $2,200 $2,200
Fund 311
2021 Street Preservation Project Pavement Preservation Projects: 2021 $2,200 $2,200
Fund 311
Total: $13,772 $17,424
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 5 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Street Reconstruction Projects
Project Name Description Start Year City Cost Total Cost
Sullivan/Euclid Concrete Reconstruct intersection in concrete 2017 $421 $2,108
Intersection(RW/CN) pavement
Argonne Road Concrete Pavement- Reconstruct pavement in concrete; 2018 $744 $3,723
1-90 to Montgomery OCI Mullan to Knox 24,OCI Knox to
Montgomery 35(2014 Rpt)
Broadway @ Argonne/Mullan Reconstruct intersections in concrete 2019 $230 $1,703
Concrete Intersections(CN Only) pavement
Total: $1,395 $7,534
Traffic Operations and Maintenance
Project Name Description Start Year City Cost Total Cost
Maribeau Pkwy&Pine(SR-27) New Traffic Signal 2016 $350 $350
Traffic Signal
North Sullivan ITS Project Extend ITS conduit and controls 2017 $123 $914
along Sullivan Corridor
Evergreen&Broadway ITS ITS along Broadway from Pines Rd 2019 $253 $1,870
(SR-27)to Evergreen,along
Evergreen from Sprague to 16th Ave.
Total: $726 $3,134
Overall Total: $23,812 $74,715
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 6 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Arterial Improvements
Project Name Description City Cost Total Cost
Mission Ave.-Flora Rd.to Barker Reconstruct with curb,sidewalks, $124 $918
Rd.(PE/RW) bike lanes and stormwater facilities;
Sullivan-Wellesley Intersection Imp Traffic Signal or Roundabout $185 $1,370
Project
Broadway Improvement Project- Extend Broadway arterial to Barker $1,042 $5,206
Flora to Barker Rd,Realign Broadway connection
east of Barker
Mission Ave.-Flora Rd.to Barker Widen&Overlay with curb, $499 $3,697
Rd.(CN) sidewalks,bike lanes and stormwater
facilities
Park Road#2-Broadway to Indiana Reconstruct to a 3-lane section with $418 $3,102
(RW&CN) curb,sidewalks,bike lanes and
stormwater facilities
Pines(SR27)/BNSF Underpass- Railroad underpass at Pines(SR-27) $255 $3,000
(PE only) /BNSF/Trent
Barker Rd-Euclid to Flora Road Reconstruct Barker to 3-lane urban $837 $4,184
section
Barker Rd Improvement Project- Widen and improve to 5-lane urban $491 $3,925
Appleway to 1-90 section,Roundabout @ Broadway,
Realign east leg of Broadway
Barker Rd Improvements-South Widen and Improve roadway to 3- $385 $2,853
City Limits to Appleway lane urban section
Barker Rd Improvement Project- Reconstruct and widen to 3-lane $632 $3,302
Spokane River to Euclid urban section
Total: $4,868 $31,557
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 1 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Bridge Projects
Project Name Description City Cost Total Cost
Sullivan Road West Bridge Reconstruct and widen west $2,360 $19,750
(southbound)bridge
Fancher/BNSF RR Overpass Joint Repair bridge expansion joints on RR $201 $201
Repair Project overpass
Argonne Rd&1-90 IC Bridge Widen Argonne Rd Bridge to 3 $1,600 $8,000
Widening Lanes,SB. New 12' sidewalks.
Barker Road/BNSF Grade Construct Grade Separation at $2,910 $29,200
Separation Barker/BNSF RR/Trent(SR290)
Total: $7,071 $57,151
Congestion Improvements
• Project Name Description City Cost Total Cost
Sprague/Barker Intersection Intersection improvements to $223 $489
Improvements improve capacity
Total: $223 $489
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 2 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Pedestrian/Bicycle Program
Project Name Description City Cost Total Cost
Seth Woodard Elem Sidewalk Imp, Construct ADA sidewalk&curb $32 $389
Mission&Park ramps on the South side of Mission
from Lily to Park,and along Park
north along the school and E
Spokane Grange frontage
Appleway Shared Use Path-Pines Construct Shared Use Pathway $450 $2,093
Rd to Evergreen Rd along abandoned RR R-O-W
Opportunity Elementary,SRTS Construct sidewalk along the east $68 $500
(Bowdish Road) side of Bowdish from 8th to 12th,and
along the south side of 11th from
Bowdish to Wilbur
Appleway Trail-Evergreen to Construct Shared Use Pathway $222 $1,645
Sullivan along abandoned Railroad Right-of-
Way
Appleway Trail-University Rd.to Extend Shared Use pathway to $102 $750
Balfour Park Balfour Park
Citywide Sidewalk Infill Project Infill gaps in Sidewalks and add $1,000 $1,000
sidewalks to access completed
portions of the Appleway Trail.
Appleway Trail-Sullivan to Corbin Shared Use Path along Old $324 $2,400
Milwaukee R/R ROW
Total: $2,198 $8,777
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 3 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Safety Program
Project Name Description City Cost Total Cost
Citywide Reflective Signal Backplates New Traffic Signal Backplates at 10 $1 $81
City Intersections
McDonald Rd ROAD DIET,16th to Bike Lanes,traffic signal $7 $616
Mission modifications,new ADA sidewalk
ramps at traffic signals.
Mission&Pines(SR-27)Intersection Intersection lane reconfiguration and $34 $335
Imp Project ROW on East and West Approches
on Mission
Sullivan-Trent(SR-290)to Wellesley Street lighting,ROW $74 $740
Corridor Lighting
Total: $116 $1,772
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 4 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Street Preservation Projects
Project Name Description City Cost Total Cost
2016 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
Appleway-Park to Dishman Mica Grind and Overlay,ADA Upgrades $161 $1,190
Preservation
2017 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
Argonne-Broadway to Indiana Pavement Preservation-Grind and $87 $640
Overlay
2018 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
Evergreen Resurfacing-Mission Grind and inlay HMA,Bike Lane $89 $660
Connector to Indiana Positive Guidance thru the 1-90 EXIT
291-A
Sprague-Sullivan to Corbin Pavement Preservation,ADA $239 $1,770
Preservation upgrade
2019 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
2020 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
2021 Street Preservation Project Pavement Preservation Projects: $2,200 $2,200
Fund 311
Total: $13,776 $17,460
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 5 of 6
City of Spokane Valley
Department of Public Works
Total Project Costs
(Including costs before and beyond the six years of this TIP)
Projects Listed by Category for the 2016-2021 Six-Year TIP
Dollars in Thousands
Street Reconstruction Projects
Project Name Description City Cost Total Cost
Sullivan/Euclid Concrete Reconstruct intersection in concrete $421 $2,108
Intersection(RW/CN) pavement
Argonne Road Concrete Pavement- Reconstruct pavement in concrete; $744 $3,723
1-90 to Montgomery OCI Mullan to Knox 24,OCI Knox to
Montgomery 35(2014 Rpt)
Broadway @ Argonne/Mullan Reconstruct intersections in concrete $230 $1,703
Concrete Intersections(CN Only) pavement
Total: $1,395 $7,534
Traffic Operations and Maintenance
Project Name Description City Cost Total Cost
Maribeau Pkwy&Pine(SR-27) New Traffic Signal $350 $350
Traffic Signal
North Sullivan ITS Project Extend ITS conduit and controls $123 $914
along Sullivan Corridor
Evergreen&Broadway ITS ITS along Broadway from Pines Rd $253 $1,870
(SR-27)to Evergreen,along
Evergreen from Sprague to 16th Ave.
Total: $726 $3,134
Overall Total: $30,373 $127,874
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Wednesday,June 24,2015 Page 6 of 6
City of Spokane Valley
Department of Public Works
Six Year Transportation Improvement Program
2016 - 2021
Dollars in Thousands
2i
Item# Project Name Primary Source City Amount Total Amount
1 Sullivan Road West Bridge BR 536 5,064
2 Mission Ave. -Flora Rd. to Barker Rd. (PE/RW) STP(U) 43 316
3 Citywide Reflective Signal Backplates HSIP 0 72
4 McDonald Rd ROAD DIET, 16th to Mission HSIP 3 574
5 Seth Woodard Elern Sidewalk Imp, Mission 5.. CDBG 30 361
Park
6 Sprague/Barker Intersection Improvements DEV 12 50
7 2016 Street Preservation Project City 2,200 2,200
8 Appleway-Park to Dishman Mica Preservation STP(U) 11 83
9 Appleway Shared Use Path-Pines Rd to STP(U) 31 145
Evergreen Rd
10 Fancher/BNSF RR Overpass Joint Repair Project City 201 201
11 Maribeau Pkwy& Pine(SR-27)Traffic Signal City 350 350
2016 Totals: $3,417 $9,416
21117
Item# Project Name Primary Source City Amount Total Amount
6 Sprague/Barker Intersection Improvements DEV 211 422
8 Appleway-Park to Dishman Mica Preservation STP(U) 145 1,071
12 2017 Street Preservation Project City 2,200 2,200
13 Argonne-Broadway to Indiana STP(U) 9 64
14 Mission & Pines(SR-27) Intersection Imp Project HSIP 34 336
16 Sullivan/Euclid Concrete Intersection (RW/CN) TIB 421 2,108
17 North Sullivan ITS Project CMAQ 14 105
18 Sullivan-Trent(SR-290)to Wellesley Corridor HSIP 12 116
Lighting
2017 Totals: $3,046 $6,422
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
o;ac';are aho,vr, n Green Funded Projects are shown in Bfue
Wednesday,June 24,2015 Page 1 of 3
Item# Project Name Primary Source City Amount Total Amount
9 Appleway Shared Use Path-Pines Rd to STP(U) 405 1,885
Evergreen Rd
13 Argonne-Broadway to Indiana STP(U) 78 576
15 Opportunity Elementary, SRTS (Bowdish Road) TAP 12 91
17 North Sullivan ITS Project CMAQ 109 809
18 Sullivan-Trent(SR-290)to Wellesley Corridor HSIP 62 624
Lighting
19 Sullivan-Wellesley Intersection Imp Project CMAQ 34 252
20 2018 Street Preservation Project City 2,200 2,200
21 Appleway Trail-Evergreen to Sullivan CMAQ 22 164
22 Appleway Trail- University Rd. to Balfour Park TAP 32 230
23 Argonne Road Concrete Pavement-1-90 to TIB 102 512
Montgomery
24 Citywide Sidewalk Infill Project City 152 152
25 Evergreen Resurfacing-Mission Connector to STP(U) 6 40
Indiana
26 Sprague-Sullivan to Corbin Preservation STP(U) 24 177
2018 Totals: $3,238 $7,712
2010
Item# Project Name Primary Source City Amount Total Amount
15 Opportunity Elementary, SRTS(Bowdish Road) TAP 56 409
19 Sullivan-Wellesley Intersection Imp Project CMAQ 150 1,116
21 Appleway Trail-Evergreen to Sullivan CMAQ 200 1,481
22 - ay TAP 70 520
23 Argonne Road Concrete Pavement-1-90 to TIB 642 3,211
Montgomery
24 Citywide Sidewalk Intill Project City 848 848
25 Evergreen Resurfacing-Mission Connector to STP(U) 84 620
Indiana
26 Sprague-Sullivan to Corbin Preservation STP(U) 215 1,593
27 2019 Street Preservation Project City 2,200 2,200
28 3r();:..Jvay; , , . Concrete STP(U) 230 1,703
Intersections(CN Only)
29 Broadway Improvement Project-Flora to Barker TIB 159 793
30 Evergreen & Broadway ITS CMAQ 36 266
31 - fora Ra. to ' - STP(U) 499 3,701
32 Park Road#2-Broadway to Indiana(RW&CN) STP(U) 20 150
33 Other Fed 128 1,501
2019 Totals: $5,537 $20,112
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
Acaec Projects sno.vn :, Funded Projects are shown in Blue
Wednesday,June 24,2015 Page 2 of 3
22
Item# Project Name Primary Source City Amount Total Amount
29 ovement Project- Flora to Berke- TIB 883 4,413
30 Evergreen & Broadway ITS CMAQ 217 1,604
32 Park Road#2-Broadway to Indiana(RW&CN) STP(U) 388 2,877
33 P - iep'-v Fir,..1F!--- „-,._ foL7,--.,-m Other Fed 128 1,501
34 2020 Street Preservation Project City 2,200 2,200
35 Appleway Trail -Sullivan to Corkin CMAQ 27 200
36 Barker Rd-Euclid to Flora Road TIB 114 571
37 Barker Rd improvement Project-Appleway to STP(U) 167 1,232
90
38 Barker Rd Improvements-South City Limits to TIB 46 339
Appleway
2020 Totals: $4,170 $14,937
ab2
Item# Project Name Primary Source City Amount Total Amount
35 Appleway Trail-Sullivan to Corbin CMAQ 297 2,200
36 Barker Rd-Euclid to Flora Road TIB 723 3,613
37 Barker Rd Improvement Project-Appleway to STP(U) 324 2,397
90
38 Barker Rd Improvements-South City Limits to TIB 340 2,515
Appleway
39 2021 Street Preservation Project City 2,200 2,200
40 Argonne Rd & I-90 IC Bridge Widening FMSIB 160 800
41 Barker Rd Improvement Project-Spokane River TIB 52 403
to Euclid
42 Barker Road/BNSF Grade Separation Other State 308 1,988
2021 Totals: $4,404 $16,116
Projects and timeframes identified in the TIP are to be considered estimates only that may change due to a variety of circumstances,and are not
intended by the City to be relied upon by property owners or developers in making development decisions.
i••:Idac:Pro;ac:3 are;ro;;n n ='_ec Funded Projects are shown in Blue
Wednesday,June 24,2015 Page 3 of 3
City of Spokane Valley •,,-;/--,
C s�nron-wens r l
2016 - 2021 Six Year TIP i Intersection Improvement w E
ProjectBarker Roatl I
-- WenesI,�i �� 1~ , i
_.,...•,-.'---"<.°BNSFGratle Separation
l,Or---Sullivan-Trent b Wellesley _I-
•
IO -__Corridor Lighting 1-^�'
.-i.�- _JI Barker Read
11 IQs__ I I Euclid lo Dl mile south f
.- 1 I OI of hent ISR 1901
Sullivan/Euclid �
\te---r-.-- '�Pines SR3 S Concrete lnlersectbnI '1'I I ��-
_ ETP '��BNSE(sem
I
Euclid Euclid ,i
Barker Rood
�,/ _ - -"'-- -\ 1 Euclid • Spokane River to Euclid
r EU'1.-1 I_ STe�t j _ IL-- MI abeou Parkway 6 Pines I5R-2n -- North Sullivan - 1p�_{,
�ttC< f _-1 /./' r_ --l t -_ ironic Signal
ITS Project I \ ,�i
�RI• I Buckeye i- ✓ '°'• _ -lir ,� II-'�_ ,' { ---t-��
9Montgome'ry/_ i� y_�Mansfield m Sullivan Road ' 1 '- '
r' •} '''-i- Indiana wed Bridge -.1,Argonne ---r-
•
Road a Ig l I -- '77.4.--: - - _ _• .
Seth Woodward Elementary IC Bridge Widening '_ Mission E Pines(SR Rnf r-
1 Intersection ImprovementProjecJ - 31 Mission 1 -_,1-_-_I^
,'-
Sidewalk improvement y 1
Argonne Road aP - i1 I1
Mission aPark / yl ° -1.-----"----Mission _ J` -JI
_ I __D Concrete ,--
.7E---
- - Mlssi C v s \r,J F`
A
•
/ ass r j -N- a-_ 1.901e Jn190 J - al--- / Resurfacing _ T BroadwayA elnpr 1
41114,- -------,
-'---=''''' I m_,, I WT_ - Evergreen Rood R s dl a 10 Flora 1 Barker
/j"% _ Argon Road -•JI O - ! i___-L-1 �- �y�_ �_-
�� �_ 4�. I Indiana T" 7 F I , 4 1 --Jr,'I - B rker Road improvement
Danaher/BNSf RR Overpass I - Jit ' ---- Bfoad Way _ I- -; ---- ApplewaYto l-90
/ .- Broad yl
rogue Ave
xri.
Argonne
`/ ''�Joll Repair Protect- --,r, f--�-t` - \Park Road.- ��4.�C nceteeIIntersections AIversayTroaIM k � �� r �PIII merdP se'=allon J /p\y.1Jay� Sp°eve/Barker
,i� S 1 _ _ h on p vemenb
i� i Bread t Indiana -,to _
-F-- _- y.._�• L i ---r_ APdeway Brall
�- --i .tel d, I Pines t Everg en - -- ` � Barker ROad Im o
..�1--'-f- I--;-1,--,--,--4----
-I "LAS ra ue7 - _ - _ _
_/ ,-- -1--rte.; -p 9 - -T I. - - - It-. _ - r r - South City Limits lo Appleway
_ �5t m' v - — r ,i - •
r 3tdt '�'•.- � �rT- _ s 4th _ 4th, Opportunity Ere ��' - o T 8 -- r 8th' i
ll Elementary
\ I f SRTS(eo tlbh Road/ l i -til - APFIee Yt B _ S Poan to Call _ - --7,-1-
....._-,--,
�
} 4th- T
�.__ 1J- N 0--- f E--'-- 1 SullivanAPWewad J-----'
- ) ,{r - - J Sullivan to Corbin
'' Park b Dishman-MI \ - TJhr/ -'
I:11+-T!17_ 8th - 8th . S� Irly�y/ - m, - 1 •-
y vatlon O N 1 a —I - - � _ D -1----'-7 T
1 7 �1 -4-- I ��- }
•
'� �T `-- -,�� / ••I ,�-,I=1a ri 16th __ McooaldR Road -2 a -- -7-7,----
� ,-1=_.__
v- • L YL - 16th � -
�r J tem to Ml..ton T /
16th
�u `� \\\� t1_-- ' 1� S'Q) - 4th.. T - I ly `
.11.7,r,,._'--,:ll
�l 1� 24th r'. 1. ` _ InI-L,—'- c / -
+-r , 3Zn' - �
' . Legend
'-�_:-i\ '<•' Project Year
k'� 't, • _ 1/, `� 2016 2019
i�l's7 .I_i_�
aI "-----.47,-!:1 g
�I 2017 2020 1
-T f-—II- 'Bl .\ ;o
(Tf S Or17_� _ 44th' ',---1---' =1 ,
tbpokane -�-4 r„ 2018 ® 2021
_� 1D .
Valle1 /� Projects Not Shown:
Sidewalk Infill Project
Reflective Signal Backplate Project
June 15,2015 2016-2021 Street Preservation Projects