15-008.05 Cameron-Reilly: Argonne Rd Corridor Upgrades strokanei0011°Naisitft `r t. 1e CHANGE ORDER NO: 5 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-052 PROJECT: Argonne Corridor Upgrades Project CONTRACT DATE: 1/8/2015 PRIME CONTRACTOR: Cameron-Reilly, LLC CIP NO: 0060 DESCRIPTION OF CHANGES This Change Order pertains to Bid Schedule: A The Contractor shall install detour route signage for Montgomery Ave based on attached Traffic Detour Plan. Item No. Description Unit Quantity Unit Price Total CO 5.1 Montgomery Detour Signage LS 1 $ 823.14 $ 823.14 $ $ 0.00 $ $ 0.00 8.7% Sales Tax $ N/A Total Amount of this Change Order(incl.Tax): $ 823.14 PHYSICAL COMPLETION Original Contract Working Days: 75 Revision By This Change Order: 0 Revisions by Prior Change Orders: 0.5 Total Revised Contract Working Days: 75.5 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 1,142,108.70 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CO#4) $ 4,535.94 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 1,146,644.64 NET THIS CHANGE ORDER $ 823.14 TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 1,147,467.78 CONTRACTOR ACCEPTANCE: if DATE: 7— " l S f The contractor hereby accepts this as, -nt under the terms • Section 1-04.4 of the original contract. jg� 2RECOMMENDED BY: � J � DATE: 77(6777.5— P /�67775 P .ject Manag APPROVED BY: �,A.jr L / `f DATE: 7((c2 Public orks Director APPROVED BY: N DATE: City Manager ATTACHMENTS: Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor, PW Project File,Project Inspector,Finance Department