2012, 05-21 Permit: SW-12001352 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001352
Permit Issued Date:
05/21/2012
Expiration Date:
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
EDGERTON
SEWER
Primary Contact
Applicant:
Address:
Phone:
Email:
OVERLAND EXCAVATION INC
OVERLAND EXCAVATION INC
P.O. BOX 277
NEWMAN LAKE, WA 99025
(509)939-7984
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
Zoning:
2420 N ELIZABETH RD
35121.5806
ORCHARD AVENUE
ORCHARD AVE- NW1/4 B206 EXC PTN WITHIN
FOL DESC< BE G AT NW COR OF E1/2 OF SD TR
206 TH W ALG N LN 12.6FT TH SLY 132. 36FT M/L
TO S LN OF SD TR TH E ALG S LN 13.5FT TO SW
COR OF E1/ 2 OF SD TR 206 TH
Water District. Orchard
Avenue Irrigation District
#6
Owner:
Address:
Phone:
Email:
ZINK, MICHAEL G
2420 N ELIZABETH RD
SPOKANE VALLEY, WA 99212-1417
Fire District: Fire District 1
Land Area: 0.2151 acres / 9367.89 sgft
CONTRACTOR INFORMATION:
General Contractor
OVERLEI951LE
OVERLAND EXCAVATION INC
24811 E WELLESLEY AVE
OTIS ORCHARDS, WA 99027
509-226-1127
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1
$125.00 $125 00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed 05/21/2012 12:3330
Printed by IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number SW -12001352 05/21/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER I5 TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed 05/21/2012 12.33.30
Printed by 115 APPPOOLWSP.NET v4.0