14-039.06 Max J Kuney: Sullivan West Bridge Ph 2 ItA-0 x n,cr 40000IrValleY CHANGE ORDER NO: 6 DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 14-039 PROJECT: Phase 2-Sullivan Road West Bridge Replacement Project CONTRACT DATE: 8/8/2014 PRIME CONTRACTOR: Max J.Kuney Company CIP NO: 0155 DESCRIPTION OF CHANGES This Change Order pertains to: Schedule A 1. Work to relocate the existing Sullivan Park sign and related Pay Item A-15 are deleted from the Contract. 2. The requirement to furnish permanent casing for the 5-foot diameter shafts at Piers 1 and 5 and related Pay Item A-48 are deleted from the Contract. 3. The requirement to place permanent casing for the 5-foot diameter shafts at Piers 1 and 5 and related Pay Item A-49 are deleted from the Contract. 4. The confined bubble curtain system specified in Section 6-05 of the Special Provisions and related Pay Item A-62 are deleted from the Contract. 5. An adjustment is made to provide compensation for the lost contribution to the Contractor's fixed costs and overhead associated with deleted Pay Items A-15,A-48,A-49,and A-62.The fixed overhead value is approximated at 12.87% of the aggregate of the deleted pay item values. Item No. Description yitt Quantity Unit Price Total Pay Item No.A-15"Relocate Sullivan Park Sign" CO-6.1(A) Credit EA (1) $ 2,000.00 $ (2,000.00) Pay Item No.A-48"Furnishing Permanent Casing CO-6.2(A) for 5-Foot Diem.Shaft"Credit LF (40) $ 55.00 $ (2,200.00) Pay Item No.A-49"Placing Permanent Casing for 5- CO-6.3(A) Foot Diam.Shaft"Credit EA (8) $ 110.00 $ (880.00) Pay Item No.A-62"Underwater Noise Attenuation CO-6.4(A) System"Credit LS (1) $ 40,000.00 $ (40,000.00) Adjustment for Lost Contribution to Contractor's CO-6.5(A) Fixed Overhead Costs LS 1 $ 5,800.00 $ 5,800.00 Subtotal $ (39,280.00) 8.7%Sales Tax(applicable only to Bid Schedules C,D.and E) $ NA Total Amount of this Chan!; Order(incl.Tax): $ 39,280.00 PHYSICAL COMPLETION Original Contract Working Days: 484 Revision By This Change Order. 0 Revisions by Prior Change Orders: 10 ...... Total Total Revised Contract Working Days: 494 CONTRACT AMOUNT THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT: ORIGINAL TOTAL CONTRACT AMOUNT $ 12,307,560.31 TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through CONS) $ 59,362.36 TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER � $ 12,366,922.67 NET THIS CHANGE ORDER . ...___. _ $ (39,280.00) TOTAL CONTRACT AMOUNT INCLUDING THIS CHANGE ORDER $ 12,327,642.67 CONTRACTOR ACCEPTANCE: ___„„„„..20 .46 DATE: 7 fLi 1 IS The contractor hereby accepts th a `-r e terms of S- •• 1-04.4 of the original contract. RECOMMENDED BY: l ,// A OA/ . /_ DATE: 7/f 5//S Project M.•=ger / APPROVED BY: �� DATE: 7/Z3Ar Public Works Director APPROVED BY: N/'¢ DATE: City Manager ATTACHMENTS: None Distribution: ORIGINAL TO: City of Spokane Valley Clerk's Office COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department,WSDOT ER Local Programs COSV Form 9/5/2014