2012, 04-02 Permit: SW-12001033 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12-001033
Permit Issued Date:
04/02/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: ACME EXCAVATING & SEWER BORING
CO.
Applicant: ACME EXCAVATING & SEWER BORING
CO.
Permit Type: SEWER Address: 6808 S LINDKE RD
GREENACRES, WA 99016
Phone: (509)228-0691
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
8018 E GRACE AVE
45072.4101
Subdivision: ORCHARD AVENUE,
REPLAT OF BLKS 151-
154
Assessor's Description: ORCHARD AVE ADD REPLAT BLK 151 TO 154-
178-179&225 E1/2 OF E1/2 OF BLK 251
Inspection Area:
Owner: FORSYTHE, CLIFFORD M
Address: 8018 E GRACE AVE
SPOKANE, WA 99212
Phone:
Email:
Water District: Orchard Fire District: Fire District 1
Avenue Irrigation District
#6
Zoning: Land Area: 0.2632 acres / 11466 sgft
CONTRACTOR INFORMATION:
General Contractor
ACMEEES963LD
ACME EXCVT & SEWER BORING CO
6808 S LINKE RD
GREENACRES, WA 99016
509-228-0691
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 04/02/2012 10:44:38
Printed by: IIS APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12-001033 04/02/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.