2015, 04-21 Permit: SW-15000351 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -15000351 Permit Issued Date: 04/21/2015
Expiration Date: 04/21/2016
Project Description: SEWER CONNECTION
Project Name: RIVER CROSSING
Primary Contact: HAYDEN HOMES, LLC
Phone: 541-923-6607
Applicant: HAYDEN HOMES, LLC
Address: 2464 SW GLACIER PL #110
REDMOND, OR 97756
Phone: 541-923-6607
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Assessor's Description:
Inspection Area:
Zoning:
2806 N HARMONY ST
55082.1801
RIVER CROSSING - PHASE 1 (AFN 6338558) LOT
1 BLOCK 1
:(509)-477-3675
Owner:
Address:
Phone:
Email:
HAYDEN HOMES, LLC
2464 SW GLACIER PL #110
REDMOND, OR 97756
541-923-6607
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District #19
Land Area: 10895 Square Feet
CONTRACTOR INFORMATION:
ALLIAEI908QB, Exp. 11/19/2016
ALLIANCE EXCAVATION INC
P 0 Box 11125 SPOKANE, WA 99211-1125
509-793-4212
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$27.12
$125.00
$152.12
$125.00
CONDITIONS:
SVRP Aquifer Boundary: Water Purveyor ability to serve statement required. If unable to serve, ?mitigation certificate? (use of private well)
from DOE prior to permit issuance.
Inside Public Transit Benefit Area
Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 04/21/2015 13.12 51 Project Coordinator Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -15000351 Permit Issued Date: 04/21/2015
Expiration Date: 04/21/2016
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed 04/21/2015 13:12:51 Project Coordinator Kathy Cummings