2014, 07-17 Permit: SW-14001058 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14001058 Permit Issued Date: 07/17/2014
Expiration Date: 07/17/2015
Project Description: SEWER CONNECTION
Project Name: TRENTWOOD
Primary Contact: SMILEY, S& C/REID, G & D Applicant: SMILEY, S& C/REID, G & D
Phone: Address: 13422 E HEROY AVE
SPOKANE, WA 99216-1204
Phone:
Email:
SITE INFORMATION•
Site Address:
Parcel Number:
13422 E HEROY AVE
45031.4001
Assessor's Description: GREEN ORCH SUB L1 B3
Inspection Area: : (509)-477-3675
Owner: SMILEY, S & C/REID, G & D
Address' 13422 E HEROY AVE
SPOKANE, WA 99216-1204
Phone:
Email:
Water District: Trentwood Irrigation District Fire District Spokane Valley Fire
#3
Zoning: Land Area: 10625 Square Feet
DETAILS.
Class Type Quantity Unit Charge Value
SEWER
FEE DETAIL'
Processing - Utilities
Utilities Permit
SEWER CONNECTION 1 $125.00 $125.00
Total Fee:
$26.64
$125.00
$151.64
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8'30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed. 07/17/2014 08.14:19 Project Coordinator: Kathy Cummings