CHANGE ORDER NO: 4
DEPARTMENT OF PUBLIC WORKS CONSTRUCTION CONTRACT NO: 16-062
PROJECT: Mansfield Avenue Connection Project CONTRACT DATE: 7/14/2015
PRIME CONTRACTOR: Inland Asphalt Company CIP NO: 156
DESCRIPTION OF CHANGES
This Change Order pertains to Bid Schedule: A
This Change Order revises the grading of the stormwater swale extending from-Sta 41+00 LT to-Sta 42+20 LT. It also
revises the Drywell 2 and a Curb Inlet Type 2. The changes are shown on the attached 8/20/14 Stormwater plan sheet 12.
Item No. Description Unit Quantity Unit Price Total
CO4.1(A) SWALE EXCAVATION. INCL. HAUL CY 21 $ 28.65 $ 601.65
Total Amount of this Change Order(incl.Tax): $ 601.65
PHYSICAL COMPLETION
Original Contract Working Days: 30 Revision By This Change Order:
Revisions by Prior Change Orders: 3 Total Revised Contract Working Days:
CONTRACT AMOUNT
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF TOTAL CONTRACT AMOUNT:
ORIGINAL TOTAL CONTRACT AMOUNT $ 516,455.00
TOTAL PRIOR CONTRACT CHANGE ORDER AMOUNT(through COO) _ $ 16 812.10
TOTAL CONTRACT AMOUNT PRIOR TO THIS CHANGE ORDER $ 533,267.10
NET THIS CHANGE ORDER _ _ $ 601.65
li TOTAL CONTRACT AMOUNT INCL INC H._...- .ORDER~ _._._ $ 533,868.75
CONTRACTOR ACCEPTANCE: !l/ ' / DATE:
The contractor hereby accepts this adJustmen he terms of Section 1-04.4 of the original contract.
RECOMMENDED BY: _4/ DATE: '9
Pr ct Manager
APPROVED BY: G DATE: g /rn/1c
Public Works Director
APPROVED BY: rU/A DATE:
City Manager
ATTACHMENTS: 8/20/14 Stormwater plan sheet 11,9/2/15 Stormwater Plan Sheet 12
Distribution:
ORIGINAL TO: City of Spokane Valley Clerk's Office
COPIES TO: Contractor,PW Project File,Project Inspector,Finance Department