2013, 01-23 Permit: SW-12002633 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002633
Permit Issued Date:
01/23/2013
Expiration Date: 01/24/2013
Project Description: SEWER CONNECTION Primary Contact: H & R COMPLETE
Project Name: GRANDVIEW ACRES COYOTE ROCK Applicant: H & R COMPLETE
Permit Type: SEWER Address: PO BOX 749
NEWMAN LAKE-, WA 99025
Phone: 509-218-8336
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessors Description
Inspection Area:
Zoning:
3524 N LOCKWOOD RD
45043.0801
GRANDVIEW ACRES PT OF L1 B5 NLY 80FT OF
SLY 240FT
Owner:
Address:
Phone:
Email:
PLOTZKI, TIMOTHY A
3524 N LOCKWOOD RD
SPOKANE, WA 99206
Water District: Irvin Fire District: Spokane Valley Fire
Water District #6
Land Area: 10240 Square Feet
CONTRACTOR INFORMATION:
General Contractor
HRCOMI'972DD
H & R COMPLETE
PO BOX 749
NEWMAN LAKE-, WA 99025
509-218-8336
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150 94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 01/23/2013 09'31'35
Printed by 115 APPPOOL\SmartGovProdApp
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12002633 01/23/2013
Expiration Date: 01/24/2013
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5.00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed 01/23/2013 09:3135 Printed by: 115 APPPOOL\SmartGovProdApp