2014, 04-24 Permit: SW-14000499 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000499 Permit Issued Date: 04/24/2014
Expiration Date: 04/24/2015
Project Description: SEWER CONNECTION
Primary Contact: FOLSOM EXCAVATING INC
Phone: 509-891-1232
Applicant: FOLSOM EXCAVATING INC
Address: 16701 E VALLEYWAY AVE
VERADALE, WA 99037
Phone: 509-891-1232
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
2304 N LONG RD
55074.3204
Owner: MCKOON, SAM A
Address: 2304 N LONG RD
SPOKANE VALLEY, WA 99016
Phone:
Assessor's Description: TR D OF SP93-896 AUDITORS #9402080532 SP Email:
BK #10 PG 38 BEING A PTN OF BLK 7 OF
GREENACRES IRR DISTRICT A
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District #19
Zoning: Land Area: 16000 Square Feet
CONTRACTOR INFORMATION:
FOLSOEI994DO, Exp. 04/20/2016
FOLSOM EXCAVATING INC
16701 E VALLEYWAY AVE VERADALE, WA 99037
509-891-1232
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$26.64
$125.00
$151.64
$125.00
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
Date Printed: 04/24/2014 12:41:13 Project Coordinator: Dawn Dompier
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000499 Permit Issued Date: 04/24/2014
Expiration Date: 04/24/2015
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 04/24/2014 12:41:13 Project Coordinator: Dawn Dompier