2014, 04-15 Permit: SW-14000416 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000416 Permit Issued Date: 04/15/2014
Expiration Date: 04/15/2015
Project Description: SEWER CONNECTION
Project Name: S GREENACRES
Primary Contact: H & S CONSTRUCTION
Phone: 509-926-8964
Applicant: H & S CONSTRUCTION
Address: 11817 E VALLEYWAY
SPOKANE VALLEY, WA 99206
Phone: 509-926-8964
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
2427 N LONG RD
55071.6301
Assessor's Description: GREENACRES IRR DIST A; TR A PER SP88-553
IN NE1/4 BLK 2 AUDITOR #8904110306 [SR EX
EXEMPT - 1AC + 84% HOUSE VALUE + GARAGE]
[SR EX TAXABLE - 0.01AC + 16% HOUSE VALUE
+ POLE BLDG]
Inspection Area: : (509)-477-3675
Owner: SWENSON, TIM R & ALICE
Address: 2427 N LONG RD
GREENACRES, WA 99016-9558
Phone:
Email:
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District #19
Zoning: Land Area: 44185.3 Square Feet
CONTRACTOR INFORMATION:
HSCON**123KF, Exp. 05/08/2015
H & S CONSTRUCTION
11817 E VALLEYWAY SPOKANE VALLEY, WA
99206
509-926-8964
DETAILS:
Class
SEWER
Type
Quantity Unit Charge Value
FEE DETAIL:
Processing - Utilities
Utilities Permit
SEWER CONNECTION
Total Fee:
$26.64
$125.00
$151.64
1 $125.00 $125.00
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
Possible Shoreline On Site
Possible Floodplain
Possible FEMA Flood Zone
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Date Printed: 04/15/2014 14:14:12 Project Coordinator: Dawn Dompier
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000416 Permit Issued Date: 04/15/2014
Expiration Date: 04/15/2015
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 04/15/2014 14:14:12 Project Coordinator: Dawn Dompier