2012, 12-31 Permit: SW-12002637 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002637
Permit Issued Date:
12/31/2012
Expiration Date: 01/01/2013
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
SOUTH BLAKE - INCLUDES ADDRESS - 515
S MAMER
SEWER
Primary Contact: ACME EXCVT & SEWER BORING CO
Applicant: ACME EXCVT & SEWER BORING CO
Address:
Phone:
Email:
6808 S. LINKE RD.
GREENACRES, WA 99016
(509)228-0691
SITE INFORMATION•
Site Address:
Parcel Number:
513 S MAMER RD
45221.9144
Subdivision:
Assessor's Description. 22 25 44 N111 FT OF S222FT OF THAT PTN OF
SW1/4 OF NE1/4 OF SE1/4 OF NE1/4 WHICH IS
ADJ TO & 150FT E OF MOORES SUBURBAN HOM
ES ADD EXC W25FT FOR CO RD
Inspection Area:
Water District: Vera
Irrigation District #15
Zoning:
Owner:
Address:
Phone:
Email:
GILES, JAMES T & CRYSTAL A
719 S MCKINNON RD
SPOKANE, WA 99212
Fire District: Spokane Valley Fire
Land Area: 0.32 Acre(s)
CONTRACTOR INFORMATION:
General Contractor
ACMEEES963LD
ACME EXCVT & SEWER BORING CO
6808 S. LINKE RD.
GREENACRES, WA 99016
(509)228-0691
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1 $125.00 $125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 12/31/2012 07:05:02
Pnnted by: 115 APPPOOL1SmartGovProdApp
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12002637 12/31/2012
Expiration Date: 01/01/2013
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5.00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed. 12/31/2012 07 05:02 Printed by 115 APPPOOL\SmartGovProdApp