1994, 12-09 Permit: 94011823 SewerSPOKANE COUNTY DEPARTMENT OF BUILDINGS
WEST 1026 BROADWAY • SPOKANE, WA 99260-0050
(509) 456-3675
SITE INFORMATION PROJECT INFORMATION
SITE ADDRESS: 1516 S MAMER-LN.
SPOKANE WA 99216
PARCEL NUMBER: 45224.9180 _-
SUBDIVISION: DHAENENS SQUARE PHASE I
LOT: 1 BLOCK: 4 ZONE: UR -7
INSPECTOR: REED OCKEY
WATER DIST: VERA
OWNER: WRS 8 ASSOC '
PHONE: 509 922 0282 I
ADDRESS: PO BOX 140841
SPOKANE WA 99214
PROJECT NUMBER: 94011823 ISSUE DATE: 12/09/94
PERMIT USE: SEWER CONNECTION - DHAENENS SQUARE 1ST (94S-1336)
APPLICANT: WRS 8 ASSOC
PHONE: 509 922 0282
ADDRESS: PO BOX 14084
SPOKANE WA 99214
CONTACT: BILL SMITH PHONE: 509 922 0782
SETBACKS -> FRONT: NA LEFT: NA RIGHT: NA REAR: NA
LENDER NAME:
PHONE:
ADDRESS:
PERMI1(S
SEWER PERMIT
CONTRACTOR
UNKNOWN
LICENSE #: UNKNOWN
-
-
_
SEWER CONNECTION
1
_
PROCESSING FEE
10.00
•
-
TOTAL PERMIT FEE
$50.00
PAYMENT SUMMARY
NOTES
PAYMENT DATE
RECEIPT#
PAYMENT AMOUNT
11/30/94 00014081 $50.00
TOTAL FEES
AMOUNT PAID'
$50.00 - . $50.00
• DUPLICATE
AMOUNT OWING
BY: CAROL FRAZIER
***FOR SEWER STUB AS -BUILT INFORMATION AND INSPECTIONS, CALL
THE COUNTY UTILITIES DEPARTMENT AT 456-3604***
CONTRACTOR OR APPLICANT IS TO FIELD LOCATE AND CONFIRM THE
ELEVATION AND POSITION OF SEWER STUB PRIOR -TO ANY OTHER
EXCAVATION
TO LOCATE, BURIED CABLES, GAS PIPING, WATER LINES, ECT.
CALL BEFORE YOU DIG (456-8000)
SEWER STUBS ARE TO BE CHECKED PRIOR TO CONNECTION TO INSURE
THAT THEY ARE CLEAR AND UNOBSTRUCTED TO THE SEWER MAIN
********* CALL FOR INSPECTION PRIOR TO COVER **********
********* 24 HOUR NOTICE REQUIRED **********
1
NOTICE ^
It is the responsibility of the permittee, not Spokane County, to see to it that the use described on the front of this permit complies with applicable codes
and requirements and that required inspections are requested. Failure to request required inspections and obtain the necessary approvals prior to
progressing beyond the point where inspections are required may necessitate removal of certain parts of the construction at the owner's/permittee's
expense. At a minimum, the following inspections ARE REQUIRED by County Code:
1. FOOTING - when forms and reinforcement are in place and prior to placement of concrete.
NOTE: This inspection includes review of the structure's setbacks from property lines. Minimum setbacks are established by County zoning
regulations. Typically, side and rear yard setbacks are measured from property lines, while setbacks for yards abutting streets are measured from
the property line or the center line of the roadway right-of-way, whichever provides the greater setback from the center line of the roadway
right-of-way. Curb lines and fence lines are not necessarily indicative of property lines. In some residential areas, the County can own as much
as 20 feet of right-of-way between your property and the actual improved street/curb. The responsibility to comply with applicable setback
provisions lies solely with the permittee —neither Spokane County nor its authorized representatives assume any responsibility for the verification
or location of your property lines. Please verify their location prior to locating your structure. Failure to properly locate the structure may require
its relocation at the owner's/permittee's expense.
2. FOUNDATION - when forms and reinforcement are in place and prior to placement of concrete. (Blocking for a manufactured home is
required to be inspected prior to the installation of skirting.)
3 FRAMING - after all framing, bracing and blocking is in place, and prior to concealing.
4. INSULATION - prior to the installation of drywall.
5 PLUMBING - after rough -in, before covering, and final.
6. MECHANICAL - rough -in of piping, before covering, metal chimneys before concealment, and final.
7 FINAL - when complete and prior to occupancy and/or use. Please provide 24 hours notice.
NOTE: In addition to inspection of the structure, this inspection includes review of site improvements (typically depicted on the approved site
plan) required by ordinance or as a condition of approval of this permit. Items such as the installation of fire hydrants, fire department access,
on-site drainage ("208 swales"), road improvements, parking, and landscaping are common requirements of a permit/site plan which must
be completed prior to final approval of a building or issuance of a Certificate of Occupancy.
In addition to the above any plumbing or mechanical systems or materials which would be concealed by framing, drywall, concrete, etc., must be
inspected prior to cover. Check with the department for "special inspections" in conjunction with commercial projects.
CALL 456-3675 FOR INSPECTIONS.
TO INSURE PROMPT SERVICE, PLEASE GIVE 24 HOUR NOTICE.
YOUR INSPECTOR IS
UNDER CERTAIN CIRCUMSTANCES, PARTS OF YOUR PROJECT MAY REQUIRE INSPECTIONS FROM OTHER AGENCIES:
• Road cuts for utilities or drives, County Engineer's Office
456 -3600 -
or State Department of Transportation
456-3000
• Sewer connection, County Utilities Department
456-3604
or City Public Works Department
625-6300
• On-site waste disposal system, Spokane County Health District • Electrical wiring, State Department of Labor and Industries
324-1560 324-2640
• Construction in a flood plain, County Engineer's Office
456-3600
EXPIRATION
Unless otherwise noted, this permit will be considered null and void by limitation of the work authorized by the permit if not commenced or is stopped
for a period of 180 days, unless a written request for an extension of the permit is received and approved by the Building Official prior to expiration.
At a minimum an inspection should be requested at least once every 180 days to assure the validity of the permit. A permit may be renewed within
one year of the date of expiration for one-half the original fee, subject to certain limitations— please call us if you have any questions.
MISTAKES?
If you think we've made an error in processing this permit or in conducting inspections pertaining to it, or find erroneous information in the permit,
please bring it to our attention immediately by filing a written request for correction within 10 working days of discovery. All such requests should be
directed to the Department of Buildings at the address found on the face of this permit.
I certify that I have examined this permit/application, state that the information contained in it and submitted by me or my agent to compile said
permit/application is true and correct, and authorize Spokane County to proceed with processing. In addition, I have read and understand the
INSPECTION REQUIREMENTS/NOTICE provisions included herein and agree to comply with same All provisions of laws and ordinances
governing this type of work will be complied with whether specified herein or not. I understand that the issuance of this permit/application and any
subsequent inspection approvals or Certificates of Occupancy shall not be construed to give authority to violate or cancel the provisions of any
state or local law regulating construction, or as a warranty of conformance with the provisions of any state or local laws regulating construction.
SIGNATURE OF APPLICATION
OWNER OR AGENT DATE
He : CO,lS_ Mawr&C.
WATER & POWER
December 7, 1994
Mr. Tom Davis
Spokane County Building Department
West 1026 Broadway
Spokane, WA 99260
Re: PE -1731-93, Water System, Dhaenens Square
Dear Mr. Davis:
601 N. Evergreen Road
P O. Box 630
Veradale. WA 99037-0630
(509) 924-3800
BEG - l)
SPOKINNOMUNTY
DEC 0904
IYISfON OF BuI WINPS
We understand that a water system must be installed prior to the issuance of any building
permits for this project. Due to the unusually heavy construction schedule that Vera's water
crew experienced during the summer and early fall of 1994, we asked the developer if this
project be scheduled for late fall or next spring, and it was scheduled for late fall. With the
early winter that we have experienced, it was impossible to complete this project prior to the
ground becoming unworkable.
There exists on this property a water service, currently being billed to the developer, that may
be utilized for the installation of a temporary water system for the 10 houses that are being
proposed for construction this winter. This meter has the capacity to provide domestic water
to these homes and has been accepted. Vera has no objection to the utilizing of this water
meter for a temporary water system, provided that the permanent system be installed prior to
June 30, 1995.
If you have any further questions please call.
Sincerely,
VER WATER & POWER
evin M. Wells
General Manager
Agency Acceptance
Washington State
Depa ! ent of H
Spokane County
H;.lth District
cc. Bill Smith
Spokane County Fire
Protection District No.11,y,t
ACTION: R SCREEN: NOPJ USERID: M5TI
H -
BUILDING PERMIT SYSTEM NOTES BY PROJECT
JURISDICTION= 11 PROJECT NUMBER= 94011653
DEPT= 1000 TOPIC= CONDITIONS
LINE DESCRIPTION
01- 01 00 SPECIAL INSPECTIONS REQUIRED ON FOUNDATIONS AT 3000 PSI
02- 02 00 RELEASED PER VERA LETTER DATED 12/7/94 FOR TEMP CONNECTION.
03-
04-
05-
06-
07-
08-
09-
10-
11-
03 -*L009 HEADER CHANGE
ACTION: A SCREEN: NOPJ USERID: MSTI
'H -
BUILDING PERMIT SYSTEM NOTES BY PROJECT
JURISDICTION= 11
DEPT= 1000
LINE
PROJECT NUMBER= 94011663
TOPIC= CONDITIONS
DESCRIPTION
01- 01 00 SPECIAL INSPECTIONS REQUIRED ON 3000 PSI CONCRETE
02- 02 00 RELEASED PER VERA LETTER DATED 12/7/94 FOR TEMP CONNECTION.
03-
04-
05-
06-
07-
08-
09-
10-
11-
01 -*L006 ADD KEY FOUND