04-028.00 Tan Moore Architects: CenterPlace ProjectAMENDMENT TO PROFESSIONAL SERVICES AGREEMENT
City of Spokane Valley
Spokane Valley Public Works Department
11707 E. Sprague Ave.
Spokane Valley, WA 99206
Agreement Amendment Number: 6
Agreement/Project Number: P3983
Date: August 23, 2004
Department: Public Works
Agreement Title: Architectural Services, Mirabeau Point CenterPlace Project
Consultant: Tan Moore Architects, P.C., 416 W. Sprague Ave., Spokane, WA 99201
You are hereby directed to make the changes listed below in the subject agreement.
Nature of the change: The agreement is modified as follows:
Item 1: Amend the scope of services as described in ARTICLE 20. Scope of Work, Part 2,
Construction Administration Phase, to include developing two change order requests and negotiating a
price with the construction contractor for the following:
1) Revising the layout of the second floor of the senior wing. The revised layout shall include deleting
the walls between rooms 231, 232, 234 and corridor 230 and adding a dance floor to this same
area. The change order shall include all designs, specifications and drawings for architectural,
structural, electrical and mechanical elements.
2) Completing the second floor of the education wing with all necessary interior finishes, electrical and
mechanical appurtenances. -- - .
The Fee for these services shall be on a time and materials basis with a maximum amount not exceed
$17, 500.00.
The changes result in the following adjustment of the agreement price and time:
AGREEMENT AMOUNT
Agreement price prior to Phis change order $076,155.65
Agreement price (increase) resulting from this change order $17,500.00
Agreement price including this change order shall not exceed $693,655.65
AGREEMENT TIME
Estimated Agreement completion date prior to the change order July 31, 2006
Agreement time (increase/decrease) resulting from this change order 0 months
Estimated Agreement completion date including this change order July 31, 2006
THE ABOVE CHANGE(S) ARE ACCEPTED THE ABOVE CHANGES} HAVE BEEN APPROVED
Tan Moore Architects, P.C. ~ Spokane Valley City Manager
bat ave Mercier, ated:
August 23, 2004
P3983, Amendment 6