2012, 08-07 Permit: SW-12001923 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001923
Permit Issued Date:
08/07/2012
Expiration Date: 08/08/2012
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
SOUTH GREEN ACRES - INCLUDES
ADDRESS 18420 E MAXWELL
SEWER
Primary Contact: CHD INC
Applicant: CHD INC
Address: PO -BOX 13717 SPOKANE WA 99213
UNKNOWN, UK 00000
Phone: 509-926-5229
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description
Inspection Area:
18418 E MAXWELL AVE
55181.2325
PLAT A
VALLEY VIEW ADD W40.33' OF N130' OF LT 7 &
E50' OF N130' OF LT 8 BLK 10
Water District:
Consolidated Irrigation
District #19
Zoning: Land Area 11700 Square Feet
Owner: PRICE-BALCH, LLC
Address: 8420 E MARINGO DR
SPOKANE, WA 99212
Phone.
Email:
Fire District: Spokane Valley Fire
CONTRACTOR INFORMATION:
General Contractor
CHDIN**126LC
C H D INC
PO BOX 13717
SPOKANE, WA 99213
509-926-5229
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG—AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed' 08/07/2012 10:45 59
Printed by: 115 APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001923 08/07/2012
Expiration Date: 08/08/2012
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 08/07/2012 10'45 59
Printed by: IIS APPPOOL\ASP.NET v4.0