2012, 04-19 Permit: SW-12001157 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001157
Permit Issued Date:
04/19/2012
Expiration Date:
Project Description: SEWER CONNECTION Primary Contact: KALIN EXCAVATION
Applicant: KALIN EXCAVATION
Permit Type: SEWER Address: 9229 E WOOLARD RD
COLBERT, WA 99005
Phone: 509-954-9101
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description
Inspection Area:
4412 N MCDONALD RD
45031.1408
TRENTWOOD
ORCHARDS
TRENTWOOD ORCHARDS BLK 44 EXC 51401&
EXC N390' & EXC W5'
Owner:
Address:
Phone:
Email:
AUBREY, JOSEPH E
4412 N MCDONALD RD
SPOKANE, WA 99216-1209
Water District: Trentwood Fire District. Fire District 1
Irrigation District #3
Zoning: Land Area: 0.6191 acres / 26969 sqft
CONTRACTOR INFORMATION:
General Contractor
KALINE*0431B
KALIN EXCAVATION
9229 E WOOLARD RD
COLBERT, WA 99005
509-954-9101
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER
SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1 $125.00 $125.00
Total Fee:
$125 00
$25.94
$125.00
$150.94
CONDITIONS:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 04/19/2012 10.34.27
Printed by. 115 APPPOOLIASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001157 04/19/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 04/19/2012 10 34.27
Printed by: 115 APPPOOLIASP.NET v4.0