2011, 08-22 Permit: 11004179 SewerSite Information
SPOKANE COUNTY
DEPARTMENT OF BUILDING & PLANNING
1026 WEST BROADWAY AVENUE • SPOKANE, WA 99260-0050
Project Information
J
Site Address: 503 S MCKINNON RD
Parcel Number: 35231.1436
Subdivision: CITY OF SPOKANE VALLEY
Block: Lot:
Zoning:
Owner: FAULKNER, ALLYSON
Address: 375 NOLAN BROWN P1,
CIIENEY, WA 99004
Building Inspector:
Water Dist:
Project Number: 11004179 Inv: 1 Issue Date: 8/22/2011
Permit Use: SEWER CONNECTION
Applicant: COURCITAINE CONSTRUCTION
19818 E SPRAGUE
GREENACRES. \VA 99016 Phone: (509) 924-5485
Contact: COURCHAINE CONSTRUCTION
19818 E SPRAGUE
GRI3ENACRES. WA 99016 Phone: (509) 924-5485
Setbacks - Front: Left: Right: Rear:
Group Name:
Project Name:
Permits
Server Connection Permit
Contractor: COURCHAINE CONSTRUCTION License #: COURCC*181 R7
SEWER CONNECTION 1 $125.00 PROCESSING FEE
1 $25 00
Total Permit Fee: $150 00
**FOR SE\VER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO
COVER. ONE WORKING DAY NOTICE REQUIRED PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL.
INSPEC'T'ION FEES APPLY AFTER 30 MINUTES.
I
**CALL. 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUN'T'Y CODE
REQUIRES T1113 INSTALLER COMPLY WITH AI,1, REQUIREMEN'T'S OF THE WA STATE DEPT OF LABOR & INDUSTRIES,
INCLUDING mos]: RELATED TO TRENCH SAFETY.
**INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS Al2E CONNECTED TO THE SEWER AND MAY
BL' REQUIRED TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE
ELEVATION AND POSITION OF SEWER STUB PRIOR TO ANY OTFIER EXCAVATION.
"SEWER STUBS AND DRY SIDE SEWERS ARE TO'BE-CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY
HAVE ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO
ALLOW FOR GRAVI'T'Y FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
**THE INSTALLER AND THIS PERMIT MUST BE PRESENTTAT TI IE J013 SITE AT THE SCHEDULED INSPECTION TIME.
BOTH S'l'ATE LAW 12CW 19.122 AND COUNTY CODE REQUIRES TI IE'INSTALLER TO GIVE NOTICE OF EXCAVATION TO
OWNERS OF UNDERGROUND FACILITIES.
Payment Summary
Total Fees AmountPaid AmountOwing
$150.00 $150.00
$0.00
Tran Date Receipt # Payment Amt
8/22/201 I
Processed By: SI'IATTG. JULIE
Printed By: Force, Faith Page 1 of 1
3675 $150.00
PERMIT
NOTICE
It is the responsibility of the applicant/permittee to see to it that the use described on the front of this permit complies with applicable codes and
requirements and that required inspections are requested. Failure to request inspections as listed below and obtain the necessary approvals before
progressing beyond the point where inspections are required may necessitate removal of certain parts of the construction at the applicant's/permittee's
or property owner's expense. At a minimum, the following inspections ARE REQUIRED by County Code:
1 FOOTING - all structures, including manufactured homes when forms and reinforcement arc in place and prior to placement of concrete.
NOTE: This inspection includes review of the structure's setbacks from property lines. Minimum setbacks are established by County zon-
ing regulations. Front, flanking, side and rear yard setbacks are measured from property lines. Curb lines and fence lines are not necessanly
indicative of property lines. In some residential areas, the County can own as much as 20 feet of right-of-way between your property and the
actual improved street/curb. The responsibility to comply with applicable setback provisions lies solely with the permittee—neither Spokane
County nor its authorized representatives assume any responsibility for the verification or location of your property lines. Please verify their
location prior to locating your structure. Failure to properly locate the structure may require its relocation at the owner's/permittee's expense.
2 FOUNDATION - when forms and reinforcement are in place and prior to placement of concrete.
3 FRAMING - after all framing, bracing and blocking is in place, plumbing. mechanical rough -in inspections have been approved. and prior to
concealing.
4. INSULATION - prior to the installation of drywall
5. PLUMBING - after rough -in, before covering, and final.
6. MECHANICAL - rough -in of piping. before covering, metal chimneys before concealment, and final
7. FINAL - all permits - when complete and prior to occupancy and/or use. Please provide 24 hours notice. NOTE: In addition to inspection of
the structure, this inspection includes review of site improvements (typically depicted on the approved site plan) required by ordinance or as a
condition of approval of this penult. Items such as the installation of fire hydrants, fire department access, on-site drainage ("208 swales"),
road improvements, parking, and landscaping arc common requirements of a permit/site plan which must be completed prior to final ap-
proval of a budding or issuance of a Certificate of Occupancy.
8. MANUFACTURED HOMES - foundation inspections prior to pouring pads. inspection of blocking/tie-downs, when completed per
manufacturers installation instructions. Final Inspection approval prior to occupancy: stairs, handrails, skirting, etc.. installations completed
WAINS Tag(s) must be affixed to the home, completed inspection record card and manufacturer's installation instructions must be available on
site.
9. SEWERS - prior to cover
10. RIGHT-OF-WAY/APPROACH - prior to placement of concrete. or. if gravel approach, after completion.
In addition to the above. any plumbing or mechanical systems or material which would be concealed by framing. drywall, concrete, etc., must be
inspected prior to cover. Check with the department for "special inspections" in conjunction with commercial projects.
FOR INSPECTIONS:
TO INSURE PROMPT SERVICE. PLEASE GIVE ONE WORKING DAY/24 HOUR NOTICE .
PARTS OF YOUR PROJECT MAY REQUIRE PERMITS AND INSPECTIONS
FROM MORE THAN ONE AGENCY.
• Building, plumbing. mechanical and fire inspections -Department
of Building & Planning 477-3675
• Construction in a flood plain - Division of Engineering & Roads 477-
3600
• Electrical wiring - State Department of Labor and Industries 324-2640
• On-site waste disposal system. Spokane Regional Health District
324-1560
• Road cuts for utilities or driveways - Division of Engineering &
Roads - 48-HOUR NOTICE REQUIRED 477-3600 or State
Department of Transportation 456-3000
• Sewer connection, Division of Utilities- 477-3604 or City Pub-
lic Works Department 625-6300
• Asbestos, Renovations. and Demolitions - Spokane Regional
Clean Air Agency 477-4727
PERMIT EXPIRATION & EXTENSION
Building permits shall automatically expire and become invalid by limitation of time three (3) years from the date of permit issuance Other permits not
issued in conjunction with the construction or completion of a building or structure shall automatically expire and become invalid by limitation of time
18 months from the date of permit issuance. The Director is authorized within his/her discretion to grant one ( I ) extension of time, for a penod not to
exceed 180 days. A request for an extension shall be made by the permit holder in writing and shall be submitted to and received by the Spokane County
Building and Planning Department prior to the expiration date of the permit and shall demonstrate just cause for the requested extension.
REFUNDS
The building official may authorize refunding: (1) Any fee paid which was erroneously paid or collected; or, (2) Not more than 80% of a permit fee
paid when no work has been done under the permit; or, (3) Not more than 80% of the plan review fee paid when an application for a permit for which
a plan review fee has been paid is withdrawn or canceled before any plan reviewing is done: or. (4) Any fee paid except on written application filed
by the original permittee not later than 180 days after the date of fee payment. Please note that application processing fees are nonrefundable unless
the application was erroneously processed.
MISTAKE?
If you think we've made an error in processing this permit or find erroneous information on the permit. please bring it to our attention immediately
by filing a written request for correction within 10 working days of discovery. All such requests should be directed to the Department of Building
and Planning at:
Spokane County Department of Building & Planning
1026 West Broadway Avenue Spokane, WA 99260
Phone: (509) 477-3675 Fax: (509) 477-4703 TDD: (509) 477-7133
REVISED 12/10 BLDG PERMIT