2012, 10-03 Permit: SW-12002313 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12002313
Permit Issued Date:
10/03/2012
Expiration Date:
Project Description:
Project Name:
Permit Type:
SEWER CONNECTION
PARKS
SEWER
Primary Contact: LAUER EXCAVATION & CONSTRUCTION
INC.
Applicant: LAUER EXCAVATION & CONSTRUCTION
INC.
PO BOX 11581
SPOKANE, WA 99220
Phone: (509)981-7954
Address:
Email:
SITE INFORMATION:
Site Address:
Parcel Number:
Subdivision:
Assessor's Description:
Inspection Area:
Zoning:
7212 E MISSION AVE
35131.0208
PARK ROAD ADDITION
PARK ROAD L8 B2
Owner:
Address:
Phone:
Email:
RYAN, JOSHUA D & JODI M
7212 E MISSION AVE
SPOKANE VALLEY, WA 99212
Water District: Spokane Fire District: Spokane Valley Fire
County Water District #3
Land Area: 11718 Square Feet
CONTRACTOR INFORMATION:
General Contractor
LAUEREC931DA
LAUER EXCAVATION & CONST
PO BOX 11581
SPOKANE VALLEY, WA 99211
509-981-7954
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1 $125.00 $125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 10/03/2012 10:13:45
Printed by: IIS APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12002313 10/03/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 10/03/2012 10:13:45
Printed by: IIS APPPOOL\ASP.NET v4.0