2012, 07-24 Permit: SW-12001813 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001813
Permit Issued Date:
07/24/2012
Expiration Date:
Project Name:
Permit Type:
S GREENACRES
SEWER
Primary Contact. ACME EXCAVATING
Applicant: ACME EXCAVATING
Address:
Phone:
Email:
6808 S LINKE RD
GREENACRES, WA 99016
509-251-8058
SITE INFORMATION -
Site Address:
Parcel Number:
Subdivision:
Assessor's Description
Inspection Area:
Zoning:
17203 E MONTGOMERY
55073.0460
SP -336-84
GREENACRES IRR DIST PLAT A; TR A OF SP
84-336 AUD # 8501210223 BK 3 PG 62;
TOGETHER WITH PTN TR Z LYG NLY OF & ADJ
TO DAF; BEG AT NW COR TR A, TH N12DEG
47MIN 21SDS E 7.41FT, TH N68DEG OOMIN 32SD
Water District:
Consolidated Irrigation
District #19
Owner:
Address:
Phone:
Email:
HOLDEN, MICHAEL
17203 E MONTGOMERY AVE
GREENACRES, WA 99016-8551
Fire District: Spokane Valley Fire
Land Area: 29690 Square Feet
CONTRACTOR INFORMATION:
General Contractor
ACMEE"982LD
ACME EXCAVATING
6808 S LINKE RD
GREENACRES, WA 99016
509-251-8058
DETAILS•
Class
Type
Quantity Unit Charge
Value
SEWER SEWER CONNECTION
FEE DETAIL'
Processing - Utilities
Utilities Permit
1 $125.00
$125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS•
Possible Floodplain
Possible Shoreline On Site
Date Printed: 07/24/2012 14:36:47
Printed by: IIS APPPOOL\ASP.NET v4 0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001813
Possible FEMA Flood Zone
Permit Issued Date:
07/24/2012
Expiration Date:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.