2012, 05-17 Permit: SW-12001363 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001363
Permit Issued Date:
05/17/2012
Expiration Date:
Project Description: SEWER CONNECTION
Project Name: S. GREEN ACRES
Permit Type: SEWER
Primary Contact: KALIN EXCAVATION
Applicant: KALIN EXCAVATION
Address: 9229 E WOOLARD RD
COLBERT, WA 99005
Phone: 509-954-9101
Email:
SITE INFORMATION:
Site Address:
Parcel Number.
17204 E MONTGOMERY AVE
55073.0511
Subdivision: PLAT A
Assessor's Description GREENACRES IRR DIST A E90' OF W290' BLK 11
Inspection Area:
Owner:
Address:
Phone:
Email:
EBERT, DANIEL C & AURORA M
17204 E MONTGOMERY AVE
GREENACRES, WA 99016-8551
Water District: Fire District: Fire District 1
Consolidated Irrigation
District #19
Zoning: Land Area: 0.5165 acres / 22500 sqft
CONTRACTOR INFORMATION:
General Contractor
KALI NE`0431B
KALIN EXCAVATION
9229 E WOOLARD RD
COLBERT, WA 99005
509-954-9101
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER
SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 05/17/2012 14:55 27
Printed by. 115 APPPOOL\ASP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001363 05/17/2012
Expiration Date:
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed 05/17/2012 14 55 27
Printed by: IIS APPPOOL ASP.NET v4.0