2014, 04-11 Permit: SW-14000382 SewerSPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000382 Permit Issued Date: 04/11/2014
Expiration Date: 04/11/2015
Project Description: SEWER CONNECTION
Project Name: SOUTH GREENACRES
Primary Contact: ANDERSON, MARK
Phone: 509-891-0772
Applicant: ANDERSON, MARK
Address: 18008 E MONTGOMERY AVE
GREENACRES, WA 99016-9306
Phone: 509-891-0772
Email:
SITE INFORMATION:
Site Address: 18008 E MONTGOMERY AVE Owner: ANDERSON, MARK
Parcel Number: 55074.3102 Address: 18008 E MONTGOMERY AVE
GREENACRES, WA 99016-9306
Phone: 509-891-0772
Assessor's Description: TR B OF SP92-721 AUDITORS #9303290244 BK 9 Email:
PG 40 BEING A PTN OF BLK 7 OF GREENACRES
IRR DIST A
Inspection Area: : (509)-477-3675
Water District: Consolidated Irrigation Fire District: Spokane Valley Fire
District #19
Zoning: Land Area: 33077 Square Feet
CONTRACTOR INFORMATION:
OWNER, Exp. 12/31/2015
OWNER PERFORMING THE WORK
SAME AS SITE ADDRESS SAME, WA 00000
509-218-7562
DETAILS:
Class
SEWER
Type
Quantity Unit Charge Value
FEE DETAIL:
Processing - Utilities
Utilities Permit
SEWER CONNECTION
Total Fee:
$26.64
$125.00
$151.64
1 $125.00 $125.00
$125.00
CONDITIONS:
Inside Public Transit Benefit Area
Plan review fee is required for all site plan reviews conducted by Spokane Valley Fire.
DRYLINE CONNECTION
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
SEWER PERMITS ARE VALID FOR ONE (1) YEAR FROM THE DATE OF ISSUANCE. FOR SEWER INSPECTIONS CALL THE UTILITIES
DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER. ONE WORKING DAY NOTICE REQUIRED. PERMIT
ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES APPLY AFTER 30 MINUTES.
Date Printed: 04/11/2014 11:05:02 Project Coordinator: Kathy Cummings
SPOKANE COUNTY UTILITIES
PERMIT
Application Number: SW -14000382 Permit Issued Date: 04/11/2014
Expiration Date: 04/11/2015
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 04/11/2014 11:05:02 Project Coordinator: Kathy Cummings