2012, 06-01 Permit: SW-12001458 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT -
Application Number: SW -12001458
Permit Issued Date:
06/01/2012
Expiration Date:
Project Description: SEWER CONNECTION
Project Name: SOUTH GREENACRES PHASE 3
Permit Type: SEWER
Primary Contact: GOBER'S LLC
Applicant: GOBER'S LLC
Address: 11215 E TRENT AVE
SPOKANE, WA 99206
Phone: 509-924-5372
Email:
SITE INFORMATION:
Site Address: 18008 E MONTGOMERY AVE
Parcel Number: 55074.3102
Subdivision: PLAT A
Assessor's Description: TR B OF SP92-721 AUDITORS #9303290244 BK 9
PG 40 BEING A PTN OF BLK 7 OF GREENACRES
IRR DIST A
Inspection Area:
Owner:
Address:
Phone:
Email:
ANDERSON, MARK
18008 E MONTGOMERY AVE
GREENACRES, WA 99016-9306
Water District: Fire District: Fire District 1
Consolidated Irrigation
District #19
Zoning: Land Area: 0.7593 acres / 33077 sqft
CONTRACTOR INFORMATION:
General Contractor
GOBERL*899L7
*GOBER'S, LLC
11215 E. TRENT AVE.
SPOKANE, WA 99206
509-924-5372
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER
SEWER CONNECTION
FEE DETAIL:
Processing - Utilities
Utilities Permit
1 $125.00 $125.00
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
Inside Public Transit Benefit Area
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
Date Printed: 06/01/2012 08:18:02
Printed by: IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT •
Application Number: SW -12001458
Permit Issued Date:
06/01/2012
Expiration Date:
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 06/01/2012 08:18:02
Printed by: IIS APPPOOL\ASP.NET v4.0