09-005.00 Larson Demolition: Old Senior Center Demolition
A ~
✓ S
O
\ CHANGE ORDER TO CONSTRUCTION CONTRACT NO: 08-021
DEPARTAAENT OF PUBLIC WORKS ,
PROJECT 072 CONTRACT C08-021 CONTRACT DATE January 15, 2009
CONTRACTOR Larson Demofftion, inc CHANGE ORDER NO 001
SCHEDULE A- PROJECT NO 00072
SCHEDULE 8 -
DE8CRIPTION OF CHANGES ~
During the project demolition, 4-1,000 gallon concrete septic tank.s were uncovered that were not listed in the contract
scope of the work. All four of the tanks were removed, two of the bmks required pumping prior to removal. Attached is
an itemized cost from the conftdor asking an additional$1,363.32 plus sales tax.
In addition, the sales tax for the state of Washington changed from 8.60/o to 8.7% on October 1, 2008. The increase adds
an addtional.1% or $93.17 to the contr~aact amount for CO # 001. The new contract amount is $102,754.46 including
the sales tax, the old contract amouirt was 101,179.36 with sales tax.
Total Change for SepUc Tanks $1,363 32 ~
SaleB Teuc 0 8 7% $118 61
Washin$ton State Tax Incnease from 8 6% to 8 7% I $9317
Total Amount of thls Chanse Order:~ $1,57510
SUBSTANTIAL COMPLETION
Original Date Prlor to this Change Order. Induding this Change Order
December 31, 2008 Deoember 31, 2008 Deoember 31. 2008
THESE CHANGES RESULT IN THE FOLLOWING ADJUSTMENTS OF CONTRACT PRICE:
ORIGINAL CONTRACTAMOUNT $101,179 36
TOTAL PRIOR CHANGE ORDER AMOUNT $0 00
CONTRACT PRICE PRIOR TO THIS CHANGE ORDER" $101,179 36
NET THIS CHANGE ORDER - 1,57510
. _ .
CONTRACT AMOUIVT IWCLUDING THIS CHAIVGE ORDER~ $102,754 46
...........a..~.
~
CONTRACTOR ACCEPTANCE DATE' cl
The contractor her+eby accepts this adJustmerrt under the o e orlginal co d tor all ork periomed
RECOMMENDED BY DATE
i West, ProJect Manager
n DATE
~
APPROVED BY
Neil Kersten, Public 7r+ector
~
AITACHMEWTS See attached oontractor proposal ~
DlsMbut/on ,
ORIGINALS TO: Contrador, City of Spokane Valley Clerk's Oftioe
COPIES TO PIN Pro1ed Flle
,
PPW/Forms/Templetes/CO (Nav C8)
C09-005
r
kd♦^ ~ ~
~ ♦ ~
LAR.SON'S DEN[OL.ITTON, INC.
P.O. B4X 4535
SPOK:ANE, WA 99220-0535 PH: 509 535 7944
FAX: 509 535-8087
CHANGE ORDER
Date: December 11, 2008
TO: City of Spokane Valley
Attn: Hal West Job Description: Old Senior Center Demo
11707 E. Sprague, Ste: 106 Project 0096 - Contract # 08-021
Spokane, WA 99206 Change Order/No. 1
RE: Septic Tank Removal
We are requesting re-reimbursement for the (4) Septic Tanks discovered to include the
removal of all, to include pumping, removal and f lling of holes.
1) 2000 210 Volvo Backhoe - Dig, removal of tanks and bury hole - 3.5 hours (Frank)
wnth operator @ $120.00 hour = $420.00.00
2) Semi Dump Truck with driver - 2.5 hours @$120.00 hr. to Haul (Z) loads concrete
to Graham Road Disposal site =$300.00
3) Damp Fee: (2) Loads concrete - 20 yrds concrete @$7.16 yrd to iaclude contractors
overhead = $143.32
_ 4) Fill Material - 80 yrds @ NC
` 5) Septic Tank Pumping X 2=$250.00 = Total $500.00 (Invoice Included)
We request an increase in contract for these materials for the above,
inaterial listed for a total of $1,363.32 plus taac
All ather terms and conditions to remain t6e same
ACCEPTED BY:
,
City of Spokane Valley Larson's Demolitio
~
~
BY: . y:
Name: Name: L. Je
Title: Title: Presi nt
Date: Date: 12/11/2008