2012, 05-04 Permit: SW-12001278 SewerSPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Application Number: SW -12001278
Permit Issued Date:
05/04/2012
Expiration Date:
Project Description: SEWER
Project Name: SUMMERFIELD PHASE II
Permit Type: SEWER
Primary Contact: ACME EXCAVATING
Applicant: ACME EXCAVATING
Address: 6808 S LINKE RD
GREENACRES, WA 99016
Phone: 509-251-8058
Email:
SITE INFORMATION:
Site Address: 4503 N PROGRESS RD Owner: BARTHOLOMEW, BRIAN J
Parcel Number: 45021.6201 Address: 4503 N PROGRESS RD
SPOKANE, WA 99216-1331
Subdivision: TRENTWOOD Phone:
ORCHARDS
Assessor's Description: BARTHOLOMEW SUBDIVISION L1 B3 Email:
Inspection Area:
Water District: Trentwood Fire District: Fire District 1
Irrigation District #3
Zoning: Land Area: 0.5046 acres / 21982 sqft
CONTRACTOR INFORMATION:
General Contractor
ACMEEES963LD
ACME EXCVT & SEWER BORING CO
6808 S LINKE RD
GREENACRES, WA 99016
509-228-0691
DETAILS:
Class
Type
Quantity Unit Charge Value
SEWER SEWER CONNECTION 1 $125.00 $125.00
FEE DETAIL:
Processing - Utilities
Utilities Permit
Total Fee:
$125.00
$25.94
$125.00
$150.94
CONDITIONS:
CALL 1-800-424-5555 BEFORE YOU DIG --AT LEAST 2 WORKING DAYS IN ADVANCE. SPOKANE COUNTY CODE REQUIRES THE
INSTALLER COMPLY WITH ALL REQUIREMENTS OF THE WA STATE DEPT OF LABOR & INDUSTRIES, INCLUDING THOSE
RELATED TO TRENCH SAFETY.
FOR SEWER INSPECTIONS CALL THE UTILITIES DEPT AT (509) 477-3604 FROM 8:30-5:00 MONDAY -FRIDAY PRIOR TO COVER.
ONE WORKING DAY NOTICE REQUIRED. PERMIT ALLOWS FOR A 30 -MINUTE INSPECTION. ADDITIONAL INSPECTION FEES
APPLY AFTER 30 MINUTES.
Date Printed: 05/04/2012 09:44:40
Printed by: IIS APPPOOLWSP.NET v4.0
SPOKANE COUNTY BUILDING AND PLANNING
PERMIT
Permit Issued Date:
Application Number: SW -12001278 05/04/2012
Expiration Date:
INSTALLER IS RESPONSIBLE TO INSURE ALL WASTEWATER DRAINS ARE CONNECTED TO THE SEWER AND MAY BE REQUIRED
TO PERFORM TESTS FOR VERIFICATION. INSTALLER IS TO FIELD LOCATE AND CONFIRM THE ELEVATION AND POSITION OF
SEWER STUB PRIOR TO ANY OTHER EXCAVATION.
SEWER STUBS AND DRY SIDE SEWERS ARE TO BE CHECKED PRIOR TO CONNECTION TO ENSURE THAT THEY HAVE
ACCEPTABLE GRADE AND ARE CLEAR AND UNOBSTRUCTED. SEWER LINES SHOULD BE CONSTRUCTED TO ALLOW FOR
GRAVITY FLOW FROM THE LOWEST LEVEL OF THE STRUCTURE.
THE INSTALLER AND THIS PERMIT MUST BE PRESENT AT THE JOB SITE AT THE SCHEDULED INSPECTION TIME. BOTH STATE
LAW RCW 19.122 AND COUNTY CODE REQUIRES THE INSTALLER TO GIVE NOTICE OF EXCAVATION TO OWNERS OF
UNDERGROUND FACILITIES.
Date Printed: 05/04/2012 09:44:40
Printed by: IIS APPPOOL\ASP.NET v4.0